13.08.2013 Views

Powering Europe - European Wind Energy Association

Powering Europe - European Wind Energy Association

Powering Europe - European Wind Energy Association

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

The studies either allocate the total extra cost or part<br />

of it to wind power. When they only allocate part of it, it<br />

is because most grid reinforcements and new transmission<br />

lines benefit all consumers and power producers,<br />

and thus can be used for many purposes, such as increased<br />

reliability and/or increased trading.<br />

Grid reinforcements should be compared to the possibility<br />

of controlling wind output or altering the way other<br />

types of generation are operated. The latter might make<br />

better economic sense, for example in cases where grid<br />

adequacy is insufficient during only part of the time because<br />

of specific production and load situations.<br />

Finally, when considerable grid reinforcements are necessary,<br />

the most cost effective solution for transmission<br />

planning would be to plan and expand the transmission<br />

network for the final amount of wind power in the system<br />

rather than planning one phase of wind power growth at<br />

a time.<br />

The national transmission upgrade cost figures tend<br />

to exclude the costs for improving interconnection between<br />

the Member States. These interconnection costs<br />

have been investigated in <strong>Europe</strong>an studies, such as<br />

Trade<strong>Wind</strong> and EWIS, as mentioned previously with scenarios<br />

up to 2030.<br />

tablE 3: GRiD UPGRaDE Costs fRoM sElECtED national<br />

systEM stUDiEs [holttinEn, 2009]<br />

Country<br />

Grid<br />

upgrade<br />

costs<br />

installed<br />

wind power<br />

capacity<br />

€/kw Gw<br />

Portugal 53 – 100 5.1<br />

The Netherlands 60 – 110 6.0<br />

United Kingdom 45 – 100 8.0<br />

United Kingdom 85 – 162 26.0<br />

chApTEr 4 Upgradingelectricitynetworks–challengesandsolutions<br />

Remarks<br />

Only additional costs<br />

for wind power<br />

Specifically offshore<br />

wind<br />

20% wind power<br />

penetration<br />

Germany 100 36.0 Dena 1 study<br />

Ireland 154 6.6<br />

Denmark 270 3<br />

Cost is for all renewables,<br />

wind is 90%.<br />

The cost adds 1-2%<br />

to electricity price.<br />

Assuming that 40%<br />

of upgrade cost is<br />

attributed to wind.<br />

EWIS calculated the costs of the network developments<br />

currently planned in order to accommodate the additional<br />

wind power between 2008 and 2015. It found they<br />

range from €25/kW for immediate measures to €121/<br />

kW wind for measures that will accommodate the ‘Optimistic’<br />

scenario in the short and longer term. The €121/<br />

kW figure represents around €4/MWh, which is similar<br />

to the additional operational costs for addressing the<br />

added variability by wind power and is a small proportion<br />

of the overall benefits of wind generation. The EWIS values<br />

are well in the range of the findings of the studies<br />

listed in Table 3.<br />

5.2 Allocating grid infrastructure<br />

costs<br />

There is no doubt that transmission and distribution infrastructure<br />

will have to be extended and reinforced in<br />

most of the EU countries when large amounts of wind<br />

power are connected. It is also clear that a far better<br />

interconnected power system is needed in <strong>Europe</strong>, if we<br />

are ever to achieve a well-functioning single market for<br />

electricity and real competition, to the benefit of consumers.<br />

However, these adaptations are needed not only to<br />

accommodate wind power, but also to connect other<br />

sources to meet the rapidly growing <strong>Europe</strong>an electricity<br />

demand and trade flows. The need to extend and reinforce<br />

the existing grid infrastructure is critical. Changes<br />

in generation and load at one point in the grid can cause<br />

changes throughout the system, which may lead to power<br />

congestion. It is not possible to identify one (new)<br />

point of generation as the single cause of such difficulties,<br />

other than it being ‘the straw that broke the camel’s<br />

back’. Therefore, the allocation of costs necessary to accommodate<br />

a single new generation plant to that plant<br />

only (for example, a new wind farm) should be avoided.<br />

Also, the discussion on financing new interconnectors<br />

should be placed in the broader context of the development<br />

of an internal electricity market, thereby not relating<br />

the benefits of grid development to individual projects or<br />

technologies. Infrastructure projects are natural monopolies<br />

and should be treated as such. Grid development<br />

benefits all producers and consumers and, consequently,<br />

its costs and benefits should be socialised.<br />

113

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!