13.08.2013 Views

Powering Europe - European Wind Energy Association

Powering Europe - European Wind Energy Association

Powering Europe - European Wind Energy Association

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

GatE ClosURE Is the point in time when generation and demand schedules are notified to the<br />

system operator.<br />

inERtia Of a power system is the sum of all rotating mass inertias of the connected<br />

generation opposing a change of system frequency. The rotational speed of<br />

synchronous generators is an exact representation of the system frequency. In<br />

the very first moments after loss of generation the inertia of the rotating machinery<br />

helps to keep the system running.<br />

intERConnECtED systEM An INTERCONNECTED SYSTEM is a system consisting of two or more individual<br />

electric systems that normally operate in synchronism and are physically connected<br />

via TIE-LINES, see also: SYNCHRONOUS AREA (UCTE).<br />

intERConnECtion An INTERCONNECTION is a transmission link (e.g. TIE-LINE or transformer)<br />

which connects two CONTROL AREAS (UCTE).<br />

loaD Means an end-use device or customer that receives power from the electric<br />

system. LOAD should not be confused with DEMAND, which is the measure of<br />

power that a load receives or requires. LOAD is often wrongly used as a synonym<br />

for DEMAND (UCTE).<br />

loaD faCtoR See CAPACITY FACTOR<br />

MinUtE REsERVE {15 Minute Reserve} See: TERTIARY CONTROL RESERVE<br />

n-1 CRitERion The N-1 CRITERION is a rule according to which elements remaining in operation<br />

after failure of a single network element (such as transmission line /<br />

transformer or generating unit, or in certain instances a busbar) must be capable<br />

of accommodating the change of flows in the network caused by that single<br />

failure (UCTE).<br />

n-1 safEty Means that any single element in the power system may fail without causing a<br />

succession of other failures leading to a total system collapse. Together with<br />

avoiding constant overloading of grid elements, (N-1)-safety is a main concern<br />

for the grid operator.<br />

nEt tRansfER CaPaCity Maximum value of generation that can be wheeled through the interface between<br />

the two systems, which does not lead to network constraints in either<br />

system, respecting technical uncertainties on future network conditions.<br />

PowER CURVE Relationship between net electric output of a wind turbine and the wind speed<br />

measured at hub height on 10 min average basis.<br />

PRiMaRy ContRol Maintains the balance between GENERATION and DEMAND in the network using<br />

turbine speed governors. PRIMARY CONTROL is an automatic decentralised<br />

function of the turbine governor to adjust the generator output of a unit as a<br />

consequence of a FREQUENCY DEVIATION / OFFSET in the SYNCHRONOUS<br />

AREA: PRIMARY CONTROL should be distributed as evenly as possible over<br />

units in operation in the SYNCHRONOUS AREA.<br />

177

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!