8 Schedule <strong>an</strong>d milestones toward GE1/1 <strong>an</strong>d 2/1 installation in LS2<br />

The overall schedule <strong>for</strong> <strong>the</strong> production <strong>of</strong> two stations GE1/1 <strong>an</strong>d GE2/1 is presented (next page) as a function <strong>of</strong><br />

months <strong>an</strong>d years from <strong>the</strong> approval <strong>of</strong> <strong>the</strong> construction project. It is assumed that <strong>the</strong> production <strong>of</strong> <strong>GEM</strong> foils<br />

will take place at CERN in <strong>the</strong> surface treatment workshop, as explained in Sect. 5.4.<br />

The two stations will be launched as soon as <strong>the</strong> project is approved <strong>an</strong>d it is estimated that assembly tests <strong>an</strong>d<br />

quality control procedures will be completed in two years per station. We will have two assembly lines in <strong>the</strong> new<br />

workshop <strong>an</strong>d <strong>the</strong> TIF. <strong>Detector</strong> tests with final electronics will be done after <strong>the</strong> delivery <strong>of</strong> <strong>the</strong> final electronics in<br />

a final stage be<strong>for</strong>e installation in LS2.<br />

Distributing <strong>the</strong> detector assembly in different sites <strong>an</strong>d institutions to optimize time <strong>an</strong>d resources has been considered.<br />

Detailed pl<strong>an</strong> <strong>of</strong> sharing <strong>the</strong> tasks will be made after project approval.<br />

The major milestones are shown in Table 17.<br />

Table 17: Summary <strong>of</strong> milestones.<br />

Milestones Activities Time (months) Time (years)<br />

Milestone 1 Baseline detector validation 11 0.9<br />

Milestone 2 Construction <strong>of</strong> 36 GE1/1 SuperChambers (SC) 28 2.3<br />

Milestone 3 Construction <strong>of</strong> 36 GE2/1 SuperChambers (SC) 32 2.7<br />

Milestone 4 VFAT final validation 24 2<br />

Milestone 5 Board production 19 1.6<br />

Milestone 6 Assembly <strong>an</strong>d QC 28 2.3<br />

Milestone 7 Final QC 27 2.3<br />

Milestone 8 Installation 40 3.3<br />