Program Administrator: Munoz Jacobs<br />

Project Manager: Charles Schirmer<br />

Project Architect: Marmon Mok Architects<br />

General Contractor: TBD<br />

No. 107 / <strong>District</strong> 1<br />

Bonham Academy<br />

Activity<br />

Description<br />

107H - Bonham [1]<br />

+ DESIGN<br />

+ BID<br />

Early<br />

Start<br />

Early<br />

Finish<br />

22FEB11A09JUN12<br />

<strong>2011</strong> <strong>2012</strong> 2013 2014 2015 2016<br />

D JAF M APMAJUJUAUSEOCNOD JAF M APMAJUJUAUSEOCNOD JAF M APMAJUJUAUSEOCNOD JAF M APMAJUJUAUSEOCNOD JAF M APMAJUJUAUSEOCNOD JAF M APMAJU<br />

+ CONSTRUCTION<br />

10JUN12 08OCT13<br />

Cost Description<br />

Original<br />

<strong>Budget</strong><br />

<strong>Budget</strong><br />

Adjustments<br />

Current<br />

<strong>Budget</strong><br />

Committed<br />

Costs Cost to Date<br />

Uncommitted<br />

Costs<br />

Projected<br />

Costs<br />

Land Improvement/Acquisition $250,000 $0 $250,000 $3,550 $583 $246,450 $250,000<br />

Design Fees $849,264 $0 $849,264 $637,443 $0 $211,821 $849,264<br />

Construction $11,046,675 $0 $11,046,675 $0 $0 $11,046,675 $11,046,675<br />

Professional Services-Other $742,871 $0 $742,871 $399,547 $82,165 $343,324 $742,871<br />

Construction-Other $111,156 $0 $111,156 $0 $0 $111,156 $111,156<br />

Abatement $0 $0 $0 $0 $0 $0 $0<br />

FF&E $216,606 $0 $216,606 $0 $0 $216,606 $216,606<br />

Other Costs $58,048 $0 $58,048 $495 $495 $57,553 $58,048<br />

Project Contingency $54,426 $0 $54,426 $0 $0 $54,426 $54,426<br />

SAISD Managed $541,563 $0 $541,563 $25,146 $25,146 $516,417 $541,563<br />

SAISD Managed-Other $0 $0 $0 $0 $0 $0 $0<br />

Miscellaneous $0 $0 $0 $0 $0 $0 $0<br />

Projected<br />

Ovr/(Undr)<br />

$0<br />

$0<br />

$0<br />

$0<br />

$0<br />

$0<br />

$0<br />

$0<br />

$0<br />

$0<br />

$0<br />

$0<br />

Totals: $13,870,609 $0 $13,870,609 $1,066,180 $108,388 $12,804,429 $13,870,609 $0<br />

Comments<br />

-Design Agreement executed with Marmon Mok Architects.<br />

-Programming Phase in progress.<br />

-Site Survey procurement in progress.<br />

-Construction start anticipated Fall <strong>2012</strong>.<br />

$14,000,000<br />

$12,600,000<br />

$11,200,000<br />

$9,800,000<br />

$8,400,000<br />

$7,000,000<br />

$5,600,000<br />

$4,200,000<br />

$2,800,000<br />

$1,400,000<br />

$0<br />

Current<br />

<strong>Budget</strong><br />

Committed<br />

Costs<br />

Cost to<br />

Date<br />

Projected<br />

Costs<br />

147