p89.<br />
<strong>Council</strong> activities and services<br />
Recreation and leisure<br />
What did it cost?<br />
Statement of cost of services for the year ending 30 June <strong>2010</strong><br />
Costs (after<br />
internal<br />
recoveries)<br />
Income Net cost Plan net<br />
cost<br />
<strong>2010</strong> 2009<br />
Net cost<br />
$000s $000s $000s $000s $000s<br />
Operational service result<br />
Recreation and sports services 26,748 12,197 14,551 14,321 13,538<br />
Events and festivals 8,085 3,383 4,702 4,191 4,366<br />
Capital revenues (15) 342 (357) (1,160) (360)<br />
Cost of service 34,818 15,922 18,896 17,352 17,544<br />
Capital expenditure<br />
Renewals and replacements 3,314 4,032 5,005<br />
Improved service levels 3,407 9,342 1,710<br />
Increased demand 640 1,545 -<br />
Total capital expenditure 7,361 14,919 6,715<br />
Explanation of significant cost of service variances<br />
Recreation and sports services<br />
Recreation and sports services has a $1 million higher net cost of<br />
service compared to 2008/09 as a result of a one off $0.5 million<br />
grant to the International Paralympic Committee Games with the<br />
remainder due to increased internal charges and staff costs.<br />
Events and festivals<br />
Amortisation costs of $0.3 million relating to events and festivals<br />
was not planned. This has been included in next year’s plan.<br />
Capital revenues<br />
Development contributions were less than anticipated.<br />
Significant capital expenditure<br />
$3.7 million was spent on the Graham Condon Leisure Centre and<br />
$0.8 million on Wharenui air and water upgrades. The remaining<br />
expenditure relates to renewals and replacements at facilities.<br />
Explanation of significant capital expenditure variances<br />
Construction of the Graham Condon Leisure Centre was delayed<br />
and $5.3 million of the 2009/10 plan will be carried forward to<br />
<strong>2010</strong>/11. The English Park artificial surface project was also delayed<br />
and $1.4 million will be carried forward to next year.