Exhibit 5A-16<br />
Per-Site Groundwater Contamination Remediation Costs*<br />
Cost element category 25 th percentile “early costs” 75 th percentile “later costs”<br />
Capital Costs $6,075,900 $21,195,000<br />
Annual O&M $98,910 $1,413,000<br />
O&M at 3% discount rate** $1,978,242 $28,260,605<br />
O&M at 7% discount rate** $1,239,522 $17,707,453<br />
Total cost at 3% $8,054,142 $49,455,605<br />
Total cost at 7% $7,315,422 $38,902,453<br />
Notes:<br />
*Cost data from Exhibits 3 and 4 in EPA “Cost Analyses <strong>for</strong> Selected Groundwater Cleanup<br />
Projects: Pump and Treat Systems and Permeable Reactive Barriers,” Office of Solid Waste &<br />
Emergency Response, EPA-542-R-00-013. February 2001 at:<br />
http://www.epa.gov/tio/download/remed/542r00013.pdf<br />
**O&M costs were capitalized over 30 years at both a 3% and 7% discount rate <strong>for</strong> use in the<br />
two estimates. This was done to simplify spreadsheet calculations.<br />
For the remaining sites expected to require remediation, but lacking groundwater monitoring requirements, EPA assumed discovery of<br />
contamination would take longer. That is, CCR contamination would have migrated <strong>for</strong> some number of years, resulting in a larger<br />
groundwater plume to remediate, or more extensive remediation. EPA assigned these sites the 75 th percentile remediation costs as the midpoint<br />
of the top half of costs. Since the first percentile time to peak results <strong>for</strong> unlined surface impoundments is six years, it is assumed that no<br />
discoveries and cleanups will be made in the first six years <strong>for</strong> these sites (three years once the two years <strong>for</strong> state adoption and one year <strong>for</strong><br />
groundwater monitoring are considered). <strong>The</strong> costs are thus spread evenly over the remaining 72 years. <strong>The</strong> present value of these<br />
remediations, accounting <strong>for</strong> the slow, but continued discovery of contaminated sites, is presented in Exhibit 5A-17 below. Further discussion<br />
of the discounted remediation costs <strong>for</strong> each year is presented in Appendix K10.<br />
Exhibit 5A-17<br />
Present Value of Future Groundwater Remediation Costs from CCR Contamination<br />
($ millions present value over 50-years)<br />
Discount Rate Subtitle C Subtitle D Subtitle D’ Baseline<br />
@ 3% $96 $1,016 $1,302 $1,587<br />
@ 7% $39 $336 $420 $504<br />
129