($80,000 per year average Subtitle C waste disposal permit cost) / (3.3) = $24,300 per non-haz waste disposal permit<br />

[((93% landfills w/permit) x (337 landfills)) + ((12% impoundments w/permit) x (158 impoundments))] x ($24,300 per permit) =<br />

$8.1 million<br />

Amortized industry cost with a capital recovery factor of 0.07246 (@7% discount rate & 50-years) = $0.59 million/year<br />

State government waste disposal permit cost:<br />

o Build estimate based on the following four RCRA Subtitle C permit-related state government activities associated with RCRA<br />

Subtitle C waste disposal permits: 51<br />

(1,215 pre-application activities) + ($27,063 application review) + ($26,846 permit issuance) + ($3,110 permit maintenance) =<br />

$58,200 average cost per Subtitle C waste disposal permit.<br />

o Assume RCRA Subtitle D (40 CFR 257, 258) waste permitting activities are less burdensome than RCRA Subtitle C waste<br />

permits. Based on factor of 3.3 times more technical standards listed in RCRA Subtitle C (40 CFR 264/265, 268, 270) compared to<br />

Subtitle D (40 CFR 257, 258), assume Subtitle D permitting costs are lower by the 3.3 factor:<br />

($58,200 per year average Subtitle C waste disposal permit cost) / (3.3) = $17,600 per non-haz waste disposal permit<br />

o State Cost Calculation:<br />

[((93% landfills w/permit) x (337 landfills)) + ((12% impoundments w/permit) x (158 impoundments))] x ($17,600 per permit) =<br />

$5.85 million<br />

Amortized state cost with a capital recovery factor of 0.07246 (@7% discount rate & 50-years) = $0.42 million/year<br />

Total baseline permit cost (industry + state government) = $1.01 million per year<br />

16. Baseline en<strong>for</strong>cement inspection<br />

Not estimated in this RIA.<br />

17. Baseline remediation of environmental releases<br />

Not estimated in this RIA.<br />

51 Source: Based on cost data from page 84 of January 2007 ASTSWMO report “State RCRA Subtitle C Core Hazardous Waste Management Program Implementation<br />

Costs Final Report” at: http://www.astswmo.org/files/publications/hazardouswaste/Final%20Report%20-%20RCRA%20Subtitle%20C%20Core%20Project.pdf<br />