<strong>Florida</strong> <strong>Seaport</strong> <strong>System</strong> <strong>Plan</strong><br />

Table 5.2<br />

Port Everglades 5-Year, 10-Year, 20-Year, and<br />

Long-Term Needs Beyond 20 Years 3<br />

Project Name<br />

Estimated Cost<br />

5-Year Vision <strong>Plan</strong>: Years 2011-2015<br />

Northport Slip 1 New Bulkheads and Reconfiguration- Phase 1 $55,000,000<br />

By-Pass Road- Phase 1 $2,000,000<br />

By-Pass Road- Phase 2 $32,000,000<br />

Cruise Terminal #2 Improvements $4,200,000<br />

Cruise Terminal #4 Improvements $13,000,000<br />

New Petroleum Tank Farm $75,000,000<br />

Slip 2 Westward Lengthening $23,000,000<br />

Midport Cruise Terminal #19 Improvements $11,430,000<br />

Cruise Terminal #19 Improvements $5,050,000<br />

Cruise Terminal #19 Improvements $13,320,000<br />

CT #18 Parking Garage $32,000,000<br />

Tracor Basin Finger Pier Replace with Catwalk + Dolphin $5,200,000<br />

Southport McIntosh Road Improvements $11,200,000<br />

Upland Enhancement $11,000,000<br />

Westlake Mitigation $12,600,000<br />

Super Post Panamax Crane (1) $12,000,000<br />

Turning Notch Expansion- Contract 1 $67,080,000<br />

ICTF – Rail and Yard $42,000,000<br />

Portwide ACOE Deepening and Widening- Design $4,000,000<br />

Total $431,080,000<br />

10-Year Vision <strong>Plan</strong>: Years 2016-2019<br />

Northport Berth 1, 2, 3 bulkheads $31,000,000<br />

CT#4 Parking Garage $32,000,000<br />

Midport Berth 16, 17, 18 bulkheads $32,000,000<br />

Multimodal Facility- Phase 1 $35,000,000<br />

Southport Turning Notch Expansion- Contract 2 $28,810,000<br />

Crushed Rock Facility $55,000,000<br />

FTZ and CBP Relocation $44,410,000<br />

Super Post Panamax Cranes (2) $24,000,000<br />

Container Yard Improvements $30,000,000<br />

Portwide ACOE Dredging/Widening $255,000,000<br />

Total $567,220,000<br />

3<br />

This table represents proposed projects that will be part of the 2009 Port Everglades<br />

Master/Vision <strong>Plan</strong> Update which is ongoing at this time.<br />

5-6 <strong>Florida</strong> Department of Transportation<br />

December 2010