Table 5.3 Port of Jacksonville Projected Needs to 2040<br />
PROJECT 2020 2025 2030 2035 2040 TOTAL<br />
Development of Permanent Cruise<br />
Terminal<br />
Harbor Deepening, Maintenance and<br />
Improvements<br />
Acquisition of Land to Support Marine<br />
Growth<br />
$0 $10,000,000 $0 $0 $0 $10,000,000<br />
$150,000,000 $50,000,000 $25,000,000 $25,000,000 $25,000,000 $275,000,000<br />
$10,000,000 $50,000,000 $10,000,000 $10,000,000 $10,000,000 $90,000,000<br />
Mayport Ferry Project $10,000,000 $5,000,000 $5,000,000 $10,000,000 $5,000,000 $35,000,000<br />
Blount Island – Improvements/Expansion $150,000,000 $150,000,000 $10,000,000 $10,000,000 $10,000,000 $330,000,000<br />
Talleyrand – Improvements/Expansion $25,000,000 $35,000,000 $50,000,000 $5,000,000 $5,000,000 $120,000,000<br />
Berth Rebuilds BIMT $40,000,000 $5,000,000 $20,000,000 $20,000,000 $20,000,000 $105,000,000<br />
Asphalt Repairs BIMT $20,000,000 $50,000,000 $10,000,000 $7,000,000 $20,000,000 $107,000,000<br />
Berth Rebuilds TMT $20,000,000 $10,000,000 $10,000,000 $10,000,000 $10,000,000 $60,000,000<br />
Asphalt Repair TMT $0 $10,000,000 $0 $5,000,000 $10,000,000 $25,000,000<br />
Intermodal Yard at Dames Point $20,000,000 $0 $0 $0 $0 20,000,000<br />
Bartram Island Dredge Expansion $20,000,000 $0 $10,000,000 $0 $10,000,000 $40,000,000<br />
PCOB New $10,000,000 $0 $0 $0 $0 $10,000,000<br />
New Terminal Development $0 $150,000,000 $150,000,000 $0 $0 $300,000,000<br />
Total $475,000,000 $525,000,000 $300,000,000 $102,000,000 $125,000,000 $1,527,000,000<br />
Source: Port of Jacksonville, October 2010.<br />