Project Area Recommendations<br />

Heritage House Landscape Improvements<br />

Project Area Priority Rankings<br />

Must-Do’s – Safety/Regulatory Items<br />

• Install concrete access ramps and sidewalks<br />

leading to the Heritage House<br />

• Ensure positive drainage away from buildings and<br />

outdoor gathering spaces<br />

Low-Cost, High-Impact Projects<br />

• Use volunteer hours to install new plant material,<br />

mulch , groundcover and edging<br />

• Install wooden white picket fencing, arbors and<br />

gates (as indicated on the design plan)<br />

• Collect oral history videos from Avila family<br />

members & package into movie format<br />

Medium & Large Projects<br />

• Remove existing asphalt alley and replace with<br />

raised community garden plots<br />

• Move large gazebo from Town Square parking lot,<br />

paint white and locate at eastern edge of<br />

Heritage House Event Lawn<br />

• Install irrigation system (drip heads to shrub beds<br />

and roter heads in Event Lawn)<br />

Medium & Large Projects (continued)<br />

• Contract with an artist to design a series of<br />

outdoor interpretive displays that document this<br />

history of the Avila family (migrant history,<br />

Hispanic American history) and the history of the<br />

Anna Flood House. Encourage the artist to use<br />

QR codes to link to recorded oral histories of the<br />

Avila family<br />

Estimated Total Project Cost<br />

(including 20% contingency):<br />

$273,466<br />

Chapter 3: Recommendations<br />

35