Standard PPA <strong>for</strong> … [Insert ‘medium’ or ‘long’, as applicable] term power procurement under Case -1<br />

and provided a copy <strong>of</strong> the same to the Seller. Further, the Procurer(s) shall indicate<br />

in wirting to the Seller, the voltage level at which supply <strong>of</strong> power is to be made to<br />

the Procurer(s).<br />

c) The Procurer(s) shall have obtained the order <strong>of</strong> the ……………… [Insert name(s) <strong>of</strong><br />

the Commission(s) in the State(s) in which the Procurer(s) are located] <strong>for</strong> adoption<br />

<strong>of</strong> the <strong>tariff</strong> under Section 63 <strong>of</strong> the Electricity Act 2003 and given a copy <strong>of</strong> the same<br />

to the Seller.<br />

3.3 Joint responsibilities <strong>of</strong> the Procurer(s) and the Seller<br />

3.3.1 The …………. [Insert “Procurer” / ”Lead Procurer”, as applicable] and the Seller shall<br />

have jointly agreed on the specific date(s) <strong>for</strong> commencement <strong>of</strong> supply <strong>of</strong> power and<br />

quantum <strong>of</strong> the Contracted Capacity to be supplied to Procurer(s) from each such date.<br />

Such mutually agreed date(s) shall not be later than the Scheduled Delivery Date, and the<br />

total quantum <strong>of</strong> power shall be equal to the Aggregate Contracted Capacity.<br />

3.3.2 These date(s) shall be mutually agreed upon within …… (…) Months [Insert same<br />

number <strong>of</strong> months, as applicable <strong>for</strong> Article 3.1] and shall be the Revised Scheduled<br />

Delivery Date(s) <strong>for</strong> the respective quantum <strong>of</strong> power.<br />

3.4 Consequences <strong>of</strong> non-fulfillment <strong>of</strong> conditions subsequent<br />

3.4.1 If any one or more <strong>of</strong> the conditions specified in Article 3.1 is not duly fulfilled by the<br />

Seller, even within………………………. [Insert as applicable “three (3) Months” in<br />

case <strong>of</strong> long term procurement / “one (1) Month” in case <strong>of</strong> medium term procurement]<br />

after the time specified under Article 3.1, otherwise than <strong>for</strong> the reasons directly<br />

attributable to the Procurer(s) or Force Majeure event in terms <strong>of</strong> Article 3.4.3, then on<br />

and from the expiry <strong>of</strong> such period and until the Seller has satisfied all the conditions<br />

specified in Article 3.1, the Seller shall, on weekly basis, be liable to furnish to the<br />

Procurer(s) additional Contract Per<strong>for</strong>mance Guarantee from any <strong>of</strong> the banks listed in<br />

Schedule 11 <strong>of</strong> this Agreement, <strong>of</strong> Rs. ……………………. (………. )[Insert Amount not<br />

less than that derived on the basis <strong>of</strong> Rs. 1.50 lakhs per MW <strong>of</strong> Contracted Capacity],<br />

which has been provided ………………….. [Insert “to the Procurer” or in the case <strong>of</strong><br />

multiple Procurers: “separately to each <strong>of</strong> the Procurers <strong>for</strong> the amount calculated prorata<br />

(and rounded <strong>of</strong>f to ……………….. [insert amount]) with the principle that amounts<br />

below Rupees …………………. [insert amount] shall be rounded down and amounts <strong>of</strong><br />

Rupees …………………. [insert amount] and above shall be rounded up) in the ratio <strong>of</strong><br />

Contracted Capacities”], within two (2) Business Days <strong>of</strong> expiry <strong>of</strong> every such Week.<br />

Such additional Contract Per<strong>for</strong>mance Guarantee shall initially be valid till the Scheduled<br />

Delivery Date, and the Procurer(s) shall be entitled to hold and/ or invoke the Contract<br />

Per<strong>for</strong>mance Guarantee, including such additional Contract Per<strong>for</strong>mance Guarantee, in<br />

accordance with the provisions <strong>of</strong> this Agreement. However, upon satisfaction <strong>of</strong> the<br />

conditions subsequent by the Seller, the additional Contract Per<strong>for</strong>mance Guarantee shall<br />

be returned by the Procurer(s).<br />

3.4.2 Subject to Article 3.4.3, if:<br />

(i) fulfillment <strong>of</strong> any one or more <strong>of</strong> the conditions specified in Article 3.1 is delayed<br />

beyond the period <strong>of</strong> …………………. [Insert “three (3) Months” in case <strong>of</strong> long<br />

term procurement / “one (1) Month” in case <strong>of</strong> medium term procurement] after<br />

…….[Insert name <strong>of</strong> Procurer(s)] 26