1.3.1 Scope<br />

Standard RFP <strong>for</strong> ….[Insert ‘medium’ or ‘long’, as applicable] term power procurement under Case - 1<br />

This bidding process is being carried out under Case – 1 bidding procedure as<br />

mentioned in the Bidding <strong>Guidelines</strong>, according to which the Bidder is free to choose<br />

any power generation source, any power generation technology and fuel type <strong>for</strong> supply<br />

<strong>of</strong> power. Further, all Bidders shall indicate the source <strong>of</strong> power generation from where<br />

the Contracted Capacity would be delivered and the type <strong>of</strong> fuel which shall be used.<br />

Supply <strong>of</strong> power is permitted from operational power plants or from power plants<br />

proposed to be commissioned on or be<strong>for</strong>e the Scheduled Delivery Date, subject to<br />

availability <strong>of</strong> reliable power over the term <strong>of</strong> the PPA.<br />

Brief scope <strong>of</strong> power procurement is given as under:<br />

Sr.<br />

No<br />

Scope Details<br />

1. Contract Period (in<br />

years)<br />

2. Requisitioned<br />

Capacity (MW)<br />

3. Minimum Bid<br />

Capacity 2<br />

……………. years [Insert no. <strong>of</strong> years depending<br />

upon medium/long term requirement]<br />

…………… MW [Insert the total aggregate<br />

quantum <strong>of</strong> power procurement in MW] <strong>for</strong><br />

……………….. [Insert base load / diurnal load /<br />

seasonal load] supply <strong>of</strong> power.<br />

During the evaluation <strong>of</strong> Bids and based on the<br />

competitiveness <strong>of</strong> the bid process, the<br />

Procurer/Authorized Representative retains the<br />

right to increase or decrease the Requisitioned<br />

Capacity by a quantum <strong>of</strong> twenty percent (20%) <strong>of</strong><br />

the quantum indicated herein.<br />

…………… MW [Insert capacity in MW]<br />

4. Load Requirement ………………… [Insert “Base Load” / “Seasonal<br />

Load” / “Diurnal Load”, as applicable]<br />

5. [Insert in case <strong>of</strong><br />

seasonal or diurnal<br />

requirement]<br />

Duration <strong>of</strong> <strong>Power</strong><br />

Procurement<br />

[Insert the following as applicable.]<br />

“For seasonal requirement:<br />

Duration <strong>of</strong> power requirement in months:……….<br />

[Insert names <strong>of</strong> months in the year]” throughout<br />

the Contract Period<br />

“For diurnal requirement:<br />

Duration <strong>of</strong> power requirement in hours: from ...<br />

hrs to …hrs and from … hrs to … hrs [Insert hours<br />

<strong>of</strong> start and end <strong>of</strong> supply <strong>of</strong> power in a day] in<br />

each day on daily basis through out the Contract<br />

2 The Minimum Bid Capacity shall be decided by the Procurer/ Authorized Representative, which may generally<br />

be the lower <strong>of</strong> the two values: 10% <strong>of</strong> the Requisitioned Capacity or 50 MW. However, the Procurer/Authorized<br />

Representative shall be free to determine any quantum <strong>of</strong> power as the Minimum Bid Capacity.<br />

………..[Insert name <strong>of</strong> Procurer / Authorized Representative ] Page 17