Chapter 3<br />
Initial Plumbing and Point of Injection<br />
The Raven Sidekick Pro ISO injection system pumps chemical into the main carrier line at the point of<br />
injection. This point must be on the pressure side of the carrier product pump and should be as close to the<br />
boom section valves as possible.<br />
Note: It is not necessary for injected products or chemicals to be measured by the flow meter.<br />
Depending upon the type of applications or chemical mixtures the injection system will normally be<br />
used with, it may be more desirable to place the injection point after the flow meter. This<br />
configuration will minimize the exposure of the flow meter to corrosive chemicals and may extend<br />
the life of the flow meter.<br />
FIGURE 2. Basic Sprayer Plumbing Diagram with Added Injection System<br />
12 Sidekick Pro ISO <strong>Installation</strong> & <strong>Operation</strong> <strong>Manual</strong>