Recirculation Check Valve<br />

<strong>Installation</strong><br />

A recirculation and priming check valve (P/N 333-0011-100) must be plumbed into the recirculation line<br />

between the 3-way valve on the outlet side of the injection pump and the chemical tank. This check valve is<br />

required to allow air to bleed off during priming of the injection pump. The recirculation and priming check valve<br />

is also necessary to allow the system to detect if the pump is primed. See Figure 1 on page 11.<br />

Note: The recirculation check valve has a 0.046” dia. hole in the poppet to allow air to pass. This check<br />

valve applies 12 PSI [83.74 kPa] to the pump during priming.<br />

Plumb the Recommended Pump Rinse System<br />

An injection pump rinse system is recommended to enhance the performance of the Sidekick Pro ISO<br />

injection pump and provide a clean method for changing between chemicals. The rinse system flushes<br />

chemical build up or residues which may collect in the injection pump.<br />

Note: Some components of the recommended rinse system may not be available from Raven. The<br />

following components may be purchased separately and plumbed as shown in Figure 9 on<br />

page 22.<br />

• Clean water supply tank<br />

• Strainer (80 Mesh)<br />

• 1/2 PSI check valve (P/N 333-0011-087)<br />

• Appropriate hose or tubing<br />

• Miscellaneous fittings<br />

<strong>Manual</strong> No. 016-0171-509 Rev. B 21<br />