CHAPTER<br />
5<br />
Chapt er 5<strong>Operation</strong><br />
Sidekick Pro ISO Priming and Calibration<br />
Before starting application of injected products, perform the following procedures to ensure the system is<br />
properly calibrated and ready for chemical application:<br />
1. Verify control console setup<br />
2. Prime the injection pump<br />
3. Calibrate the injection pump<br />
Verify Control Console Settings<br />
Review the Virtual Terminal Calibration section on page 31 and verify that the correct settings for the chemical<br />
injection product are programmed for the correct product node or product number.<br />
Prime the Injection Pump<br />
1. Open the hand valve(s) between the supply tank and injection pump.<br />
2. Set the hand valve on the injection pump outlet to recirculate product back to the supply tank.<br />
3. Lift the plunger handle on the pump calibrator to the top of the calibration cylinder.<br />
4. Verify the following conditions are present:<br />
a. Vacuum pressure for the injected product must be less than 5.5 PSI [37.92 kPa]<br />
b. Injection pump discharge pressure must be less than 12 PSI [82.7 kPa]<br />
c. Injection product pump mode must be set to “CAL/PRM” (Calibration/Prime)<br />
d. Injection pump product master switch must be set to on<br />