32 DESCRIPTION OF THE WIND FARM<br />

• The upper part of the tower<br />

• The nacelle<br />

• The rotor and the rotor blades<br />

The different parts will be transported to the site<br />

with special installation vessels that are equipped with<br />

cranes.<br />

Depending on the weather, the installation of each<br />

wind turbine usually takes one to two days. As weather<br />

conditions usually are favourable, it will probably take<br />

place during the period April to September.<br />

The installation is planned to be carried out in two<br />

phases during two calendar years. There are four reasons<br />

<strong>for</strong> this.<br />

Firstly, one can monitor the <strong>environmental</strong> consequences<br />

during the Þ rst phase to determine if something<br />

unexpected has occurred.<br />

Secondly, one can make use of the knowledge<br />

gained during installation to optimise the construction<br />

of the foundations.<br />

Thirdly, it will be natural to divide the cable laying<br />

into two phases as just over 300 MW can be connected<br />

to each of the two trans<strong>for</strong>mer stations (read more<br />

about this in the report “Elektrisk integrering av <strong>Kriegers</strong><br />

Flak II I det Sydsvenska elnätet”, attachment 13.1).<br />

Finally, only monopiles will be used during the Þ rst<br />

phase, resulting in a fairly simple installation process.