impacted property. However, using this data provides for a consistent valuation<br />

across all properties being considered. Therefore, it offers a reasonable surrogate to a<br />

more detailed property-appraisal process that would be conducted in a future project<br />

phase.<br />

The potential property acquisitions were divided into two primary categories: partial<br />

and full. The land values for partial takings were based on an average value per acre<br />

of land for all properties expected to be impacted by the option being evaluated. For<br />

full takings, which involve the <strong>com</strong>plete acquisition of land and/or buildings, the<br />

total assessed property value contained in the assessment database was used to<br />

estimate the impact. The assessment ratio of properties in Topsham reportedly was<br />

close to 100 percent at the time of this analysis; therefore, the estimated cost impacts<br />

of Topsham properties may reflect more closely potential purchase prices. However,<br />

according to the Town of Brunswick assessor, the assessment ratio of real property<br />

was estimated at only 60 percent of market value, which means that potential<br />

acquisition costs for project options in Brunswick could be significantly higher than<br />

the estimates provided.<br />

5.1.5 Environmental Evaluation – Resources and Methods<br />

Understanding the potential impacts on environmental and social resources is<br />

another important element of the Feasibility Study. To review these issues, an<br />

impact analysis of each option was conducted.<br />

As described in Chapter 2, available GIS data for the Study Area were obtained<br />

from various state agencies, MaineGIS, and the local level. In addition, existing<br />

environmental information was verified and updated in the field based on a<br />

reconnaissance-level effort. Information pertaining to ROW and property in the<br />

Study Area was obtained by 2008 and 2009 GIS parcel mapping, including<br />

assessment records, provided by the Towns of Brunswick and Topsham,<br />

respectively.<br />

Potential impacts then were calculated using a GIS overlay analysis, in which the<br />

footprint of each roadway option was overlaid onto the various environmental<br />

resources. Table 5.1-2 summarizes the metrics used to evaluate these resources.<br />

Impacts presented in this Feasibility Study must be interpreted cautiously. First,<br />

only direct impacts were considered. However, certain resources (i.e., historic<br />

buildings and historic districts) can be affected indirectly. Second, all identified<br />

impacts are preliminary estimates because they are based on preliminary rough<br />

grading without site-specific survey contours or detailed engineering. Third,<br />

resource mapping relies primarily on landscape-level environmental data rather<br />

than detailed site-specific studies that would be required during a formal NEPA<br />

or permit evaluation. The impacts, however, are still useful and appropriate for<br />

<strong>com</strong>paring the relative impacts of options within a strategy.<br />

Conclusions 142