2003 - Annual Report - <strong>EDP</strong><br />
• Ribatejo Thermoelectric Power Station<br />
Through TER, <strong>EDP</strong> Produção is building a combinedcycle<br />
thermoelectric power station located next to the<br />
Carregado Power Station, designed to operate under<br />
the Non Binding Generation regime, which was<br />
integrated in CPPE from January 1, <strong>2004</strong>.<br />
This new project has three generating groups with a<br />
unit power at emission of 392 MW. The first stage<br />
involves the adjudication of the construction of group’s<br />
1 and 2, with an option on the adjudication of group 3.<br />
In December, <strong>EDP</strong> took the decision to exercise the<br />
option on the construction of group 3 and its<br />
construction contract is currently being drawn up. It is<br />
expected to come into service in April 2006, six months<br />
ahead of the date initially <strong>plan</strong>ned.<br />
Relevant factors during 2003 include:<br />
a) group 1: the gas turbine was lit <strong>for</strong> the first time on<br />
September 5 and the first synchronisation with the<br />
220 kV grid took place on September 12, the<br />
nominal load of the gas turbine having been<br />
achieved on September 29. The first start-up of the<br />
steam turbine took place on October 14. The group’s<br />
nominal power (392 MW) was achieved <strong>for</strong> the first<br />
time on November 19. The first period of 10 days of<br />
experimental service was successfully carried out in<br />
December;<br />
b) group 2: the commissioning of the equipment<br />
<strong>for</strong>ming part of the group took place in December;<br />
c) the conditions governing the supply of the energy<br />
produced during tests were agreed with <strong>EDP</strong><br />
Distribuição, with an accumulated emission of 203<br />
GWh during this period;<br />
d) within the scope of licensing, the Environmental<br />
License issued by the Environment Institute and the<br />
Group 1 Operating License, issued by the DGE,<br />
were received during December.<br />
Special Regime Generation<br />
Generation based on renewable sources totalled 1 041<br />
GWh, about 27.7% more than in 2002, chiefly the result of<br />
the increase of hydroelectric generation (161.5%).<br />
Special Regime Generation<br />
<strong>EDP</strong> Group GWh<br />
• Hydroelectric Generation<br />
During 2003 the net generation figures <strong>for</strong> HDN and<br />
Hidrocenel were 131 GWh and 47 GWh respectively, an<br />
increase of 30.5% and 11.5% compared with 2002 (<strong>EDP</strong><br />
Energia’s net generation in the PRE was 19 GWh,<br />
142.6% more than in 2002).<br />
In connection with this type of generation in 2003<br />
attention is drawn to the following:<br />
a) the acquisition by HDN, of Hidrinor – Hídrica do<br />
Norte, S.A., which runs the Labruja hydroelectric<br />
power station;<br />
b) the commissioning of the Hidrocenel Lagoa<br />
Comprida power station; and<br />
c) the progress made in the technical and economic<br />
valuation processes and negotiations involving the<br />
purchase of two companies owning minihydroelectric<br />
power stations.<br />
• Wind Farm Generation<br />
At the end of 2003, ENERNOVA had five wind farms in<br />
operation – Fonte da Mesa, Pena Suar, Cabeço Rainha,<br />
Cadafaz and Serra do Barroso – with a total installed<br />
capacity of 65 MW, an increase of 24 MW (59%)<br />
compared to the end of 2002, or about 25% of the total<br />
installed wind-farm capacity in mainland Portugal.<br />
78/79