01.12.2012 Views

Nuclear Energy

Nuclear Energy

Nuclear Energy

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

The second and more important reason is design problems with the EPR reactor. In order to<br />

cut down lead time, the Finnish and French authorities allowed construction of Olkiluoto and<br />

Flamanville reactors to begin before the design was finalised and fully approved by them. Whereas<br />

the correct procedure is that designs should be complete and full safety regulatory approval given<br />

before construction is allowed to begin, so that in case there are design changes, these do not disrupt<br />

construction. ccclxviii<br />

Over time, the Finnish and French regulators realised that there were serious design<br />

problems with the reactor. They found the design of the control and instrumentation system – the<br />

nerve center of the reactor – to be at odds with basic principles of nuclear safety. Its back up system<br />

was not sufficiently independent of the main system for it to be able to provide reliable back-up if<br />

the main system fails – in other words, if the main control system fails, there is a risk that the back-<br />

up system will fail for the same reason. ccclxix And so they asked for design modifications. But<br />

because construction had already begun on the basis of the old design, making these modifications<br />

was difficult. ccclxx This is another reason for the serious quality control problems, construction<br />

delays and cost overruns of the two reactors.<br />

The <strong>Nuclear</strong> Installations Inspectorate (NII) of the UK, which is conducting a detailed<br />

review of the EPR design, has also expressed similar concerns about the design of the control and<br />

instrumentation (C&I) system of the EPR in a letter to Areva. In its letter, the NII said the EPR<br />

technology was significantly compromised because of the interconnectivity of what were meant to<br />

be independent systems designed to operate the plant and ensure its safety. The letter also<br />

highlighted concerns about the absence of safety display systems or manual controls that would<br />

allow the reactor to be shut down, either in the station’s control room or at an emergency remote<br />

shutdown station. ccclxxi<br />

The US <strong>Nuclear</strong> Regulatory Commission, which is also carrying out a review of the EPR<br />

design, has in a communiqué issued as recently as July 23, 2010, also expressed reservations on the<br />

control systems and other issues. ccclxxii<br />

The Roussely Report<br />

As the problems with construction of the EPRs at Olkiluoto and Flamanville mounted, the<br />

French government ultimately acknowledged that all was not well with the French nuclear industry<br />

and in October 2009 commissioned a former CEO of EDF, Francois Roussely, to review what was<br />

going wrong with the EPR. The report, The Future of the French Civilian <strong>Nuclear</strong> Sector was<br />

published in July 2010. Roussely stated in his report that experience with Olkiluoto and Flamanville<br />

had ‘seriously shaken ... the credibility of the EPR model and of the capacity of the French nuclear<br />

industry to succeed in new nuclear plant construction.’<br />

He attributed the problems to the complexity of the EPR model "including ... the redundancy<br />

of safety systems.” The report suggested that this complexity “is certainly a handicap for its<br />

implementation and therefore its cost”, and partly explains the difficulties encountered in Olkiluoto<br />

and Flamanville. ccclxxiii<br />

91

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!