Table 7-3<br />

Support Equipment<br />

1[tern Qw Support Equipment Rental Period<br />

1 2 Trailers: decon (change) fitted w/showers, lavatories, 8- months<br />

water closets. Trailer to also be equipped with hot<br />

water heaters and HV/AC units and generator. Each<br />

trailer unit to accommodate 25 people.<br />

2 4 Trailers: (office/breaks) -10’ x 40’ 6- months<br />

3 1 Truck: Fueling (diesel only) capacity 2,500 gals.<br />

(Alternate to equipment supplier fueling).<br />

4 6 Pickups: 4-wheel drive (Ranger) 6- months<br />

5 40 Radios and base stations for 0U2 area only 6- months<br />

6 2 Pressure washer: hot water 1500 psi 6- months<br />

7 2 Safety shower/eye wash (portable) 6- months<br />

8 4 Meteorological station 6- months<br />

9 4 Radiation detectors 6- months<br />

10 4 Photo ionization detectors 6- months<br />

11 4 Chemical warfare great detectors 6- months<br />

12 4 Combustible gas meters 6- months<br />

13 4 Portable decon stations (probably a purchase) 6- months