● Trucks will transport material to the designated stockpiles at Areas B through F.<br />

● These areas will be brought to ftish grade using dozers and graders.<br />

vegetative cover will come from the stockpile of grubbed material.<br />

Part of the<br />

● Material intended for the vegetative cover will be tested in accordance with<br />

EM200-1 -2 to confirm the material is not contaminated. Contaminated soil will<br />

be placed under the landfill cap.<br />

2.6.4.2 Areas B through F<br />

The procedures for excavation of overburden from Areas B through F, presented in Figure 2-15,<br />

Excavation Plan - Areas B to F, will be as follows:<br />

2.6.5<br />

● Prior to transporting overburden, the perimeter limits of refuse trenches will be<br />

determined using the existing surveys, surface features, and limited exploratory<br />

trenching. Stockpiles will be located outside these units.<br />

● Overburden will be removed from Areas B through F using dozers pushing to the<br />

perimeter limits of the area. In the larger areas, material will be windrowed and<br />

loaded out with front end loaders.<br />

● Overburden removal is the extent of excavation in Areas B through F, and will not<br />

leave less than nine inches of cover over the existing refuse trenches.<br />

Backfill<br />

Backfill activities will be performed in Areas A through F as described in the following sections.<br />

2.6.5.7 Area A<br />

Area A does not require low-permeable landfill cover and will be graded to an elevation of 165<br />

feet after removal of refuse. The methods for backfilling Area A are as follows:<br />

● The 165 Bench and the 180 Bench will be backfdled using material from the 180<br />

Bench and 200 Bench by using dozers, a loader and trucks.<br />

● The backfill material will be placed in loose lifts of 9 to 12 inches and moisture<br />

conditioned.<br />

● The backfdl will be compacted using smooth drum vibratory compactors to 85<br />

percent of the maximum dry density based on standard proctor testing.<br />

SJ16-24-961SA~~C~O~ OU21RAWP.RV 1<br />

2-25