2.1.3 Ductile Iron Pipe<br />

● Pipe: AWWACl51, working pressure not less than 150 psi, or to match<br />

existing.<br />

● Mechanical Fittings: AWWA Cl 10, rated for 150 psi<br />

● Push-On Fittings: AWWA C 110 and AWWA Cl 11, rated for 150 psi<br />

s Push-On Joints: AWWA Cl 11<br />

● Mechanical Joints: AWWA Cl 11 as modifiedbyAWWAC151<br />

● Flanged Joints: AWWA Cl 15<br />

2.1.4 Steel Pipe<br />

● Pipe: AWWA C200.<br />

● Fktings: AWWA C200, fabricated in compliance with AWWA C208<br />

● Mechanical and Push-On Joints: AWA C200<br />

● Flanged Joints: AWA C207<br />

2.2 MISCELLANEOUS MATERIALS<br />

2.2.1 Buried Steel Pipe Coating: AWWA C203<br />

2.2.2 Plastic Marking Tape: In accordance with Section 02222, EXCAVATION,<br />

TRENCHING, AND BACKFILLING FOR UTILITIES.<br />

PART 3 EXECUTION<br />

3.1 INSTALLATION<br />

3.1.1 Cut pipe in a neat manner with mechanical cutters. Use wheel cutters where<br />

practicable. Smooth sharp and rough edges and remove loose material from the<br />

pipe before laying.<br />

SJ/5-13-961SACIZRC fITORDOU2M2732 02732-4 Sanitary Sewerage Systems