3.1.2 Lay pipe with bells facing the direction of laying. Before lowering and while<br />

suspended, inspect the pipe for defects. Lay pipe in accordance with the<br />

following:<br />

● Ductile Iron: AWWA C600.<br />

● Steel: AWWA C600.<br />

● Polyvinyl Chloride: Manufacturer’s instructions.<br />

● Polyethylene: ASTM D2774.<br />

3.1.3 Join pipe in accordance with manufacturer’s instructions.<br />

3.1.4 Form and place concrete thrust blocks at each elbow or change of direction of<br />

force mains.<br />

3.1.5 Install plastic marking tape continuous over top of non-ferrous pipe below finish<br />

grade.<br />

3.2 FIELD QUALITY CONTROL<br />

3.2.1 Air Pressure Test: SALINAS Standard Specification Section71.<br />

3.2.2 Water Pressure Test: SALINAS Standard Specification Section 71.<br />

3.3 CLEANUP<br />

Upon completion of the installation of the sewer lines and appurtenances, remove debris<br />

and surplus materials resulting from the work.<br />

END OF SECTION<br />