THE MUNICIPALITY OF LAMBTON SHORES<br />

D.C.S. Report No. 56-2012 Wednesday July 7, 2012<br />

TO:<br />

FROM<br />

RE:<br />

Mayor Weber and Members <strong>of</strong> Council<br />

Brent Kittmer, Director <strong>of</strong> Community Services<br />

Arkona Sidewalks<br />

RECOMMENDATION:<br />

That By-law 78-2012 authorizing the Mayor and Clerk to sign<br />

the contract agreement with JD McPhee for sidewalk<br />

replacement in Arkona at the intersection <strong>of</strong> Arkona Road<br />

and Townsend Line be approved; and further that D.C.S.<br />

Report No. 56-2012 providing direction to staff be received.<br />

REPORT<br />

This report is presented to Council for direction regarding two issues related to sidewalks<br />

in Arkona.<br />

Sidewalk Replacement (Arkona Road and Townsend Line)<br />

Community Services staff is currently working to replace the sidewalk on the south west<br />

side <strong>of</strong> the intersection <strong>of</strong> Arkona Road and Townsend line. This project involves the<br />

removal <strong>of</strong> the interlocking brick and replacing it with poured concrete. <strong>The</strong> original scope<br />

<strong>of</strong> the project called for the concrete to be colored and stamped so that the finished<br />

product resembled interlocking brick. However, when this project was tendered in 2011 is<br />

was well over budget and these two portions <strong>of</strong> the job were deleted.<br />

<strong>The</strong> contract for the 2012 capital sidewalk replacements was tendered with a total budget<br />

<strong>of</strong> $62,837.00. <strong>The</strong> tender submitted by C&G Concrete was $38,883.77 inclusive <strong>of</strong> HST<br />

and the net cost to the municipality (less the HST rebate) is estimated to be $35,016.04.<br />

This represents an approximate savings compared to budget <strong>of</strong> $27,000.<br />

Given this savings, staff has priced the cost to add the colored concrete option back into<br />

the sidewalk replacement at Arkona Road and Townsend Line. Staff feels that this option<br />

presents a beatification <strong>of</strong> the area compared to the uncolored concrete and the final<br />

product will better resemble the original condition <strong>of</strong> the sidewalk. Concrete stamping will<br />

remain removed from the project. <strong>The</strong> cost to make this change has been quoted at<br />

$11,000.<br />

Staff requires direction from Council should they wish to make this change.<br />

Also, upon review <strong>of</strong> the file staff have noted that an authorizing by-law was passed<br />

authorizing the Mayor and the Clerk to sign the contract for this project. As a housekeeping<br />