2012-13 <strong>Technology</strong> Infrastructure New Items<br />

Celebration High Data Outlet Replacements 5,000.00 Replacement of current installation with a mix of wall data outlets and power<br />

pole data outlets to remove all data outlets from floor box locations eliminating<br />

the need for routine repairs. Building 8 only.<br />

Cypress Elementary Prep Work to support E-Rate 4,000.00 1) Data Modification - Document locations of all cabling and components<br />

installed in existing patch panel and VDBB at 3 locations. 2) Racks - Relocate data<br />

patch panels and fiber optic LIU's at 7 rack locations.<br />

Gateway High Backbone Cable Upgrade 275,000.00 Replace backbone cable and upgrade to new fiber optic cabling, copper<br />

include new intrusion detection cabling to all buildings and in process<br />

demolition of all old cabling.<br />

Gateway High Prep Work to support E-Rate 125,000.00 1) Data Modification - Document locations of all cabling and<br />

components installed in existing patch panel and VDBB at 11 locations.<br />

2) Racks - Relocate data patch panels and fiber optic LIU'S at 14 rack<br />

locations. 3) Fiber Optic Cabling - Installation of single mode at 8<br />

locations and multi-mode fiber optic cabling at 17 locations. 4)<br />

Cabinets - Installation of CHATSWORTH "MEGA FRAME" cabinets at<br />

2 locations.5) Press Box - Install conduit, cabinet and cabling, 1<br />

location. SOW Division 27<br />

Gateway High Data Drop Building 15 3,000.00 Add Data Drop in 15-103, 104, 106 for a network computer lab<br />

Harmony High Cyclical UPS Systems 110,000.00 UPS Upgrade and replacement. Redundant Core Site. MDF generator<br />

for Internet Voip.<br />

Parkway Middle Prep Work to support E-Rate 4,000.00 Power - Install NEMA L-6 30R power receptacle(s) at 2 locations.<br />

Pleasant Hill Elem Prep Work to support E-Rate 23,500.00 1) Data Modification - Document locations of all cabling and<br />

components installed in existing patch panel and VDBB at 7 locations.<br />

2) Racks - Relocate data patch panels and fiber optic LIU'S at 7 rack<br />

locations. 3) Fiber Optic Cabling - Installation of single mode at 5<br />

locations and multi-mode fiber optic cabling at 0 locations. Power, fiber<br />

cabling and data installation....SOW Division 27<br />

Thacker Ave Elem MDF Renovation 30,000.00 Requirements to bring this closet up to like new condition with respect to<br />

the renovated areas of the campus are: 1) New voice and data backboard<br />

installed on all walls replacing dilapidated makeshift installation. 2)<br />

Reconfiguration of wall fields striped with paint and stencils identifying<br />

specific wall field equipment areas. 3) Reconfiguration of grounding<br />

system to provide adequate coverage to all applicable areas specifically<br />

where currently lacking. 4) Extending existing two post racks to current<br />

standard of four feet distance from backboard to permit ease of work<br />

behind racks. 5) Inclusion of one additional two post rack for expansion<br />

purposes. 6) Installation of new ladder rack for cable transitions around<br />

entire perimeter of room extended to the top of each two post rack at<br />

eighty-four (84) inches A.F.F. 7) At new two post rack area installation<br />

of two (2) NEMA L630R clean power receptacles at eighty inches<br />

A.F.F. 8) Above ceiling installation of additional cabling support where<br />

required. 8) All new and existing conduit penetrations from exterior to<br />

interior to be professionally secured and sealed for prevention of outside<br />

water and weather intrusion. 9) Relocation of APC Server Rack from<br />

different room in same corridor to the MDF. 10) Relocation of the DX<br />

HVAC unit currently installed in the same room where the APC Server<br />

Rack is installed in same corridor. Re-establish operability of the current<br />

existing DX Unit in the MDF space. 11) Retouch of all space paint to<br />

provide like new appearance. Replacement of chipped, damaged or<br />

cracked ceiling tiles as found wanting. 12) Thorough cleaning of interior<br />

of the space, racks and equipment vacuum and wipe down, top to<br />

bottom, wall to wall.<br />

Multiple Facilities Server Refresh - $40,000 per<br />

school @ 5 schools per year<br />

200,000.00 Money would be used to refresh middle and high school core domain controllers<br />

and establish a 5 year refresh on servers.<br />

Multiple Facilities Set aside for emergency<br />

320,000.00<br />

infrastruture switching (MDF,<br />

IDF switching equipment)<br />

Total 1,099,500.00<br />

<strong>2013</strong> Educational <strong>Technology</strong> <strong>Plan</strong> 57/91 <strong>School</strong> <strong>District</strong> of <strong>Osceola</strong> <strong>County</strong> Florida