Facility Project Name Scope of Work Estimated Cost ($)<br />

TECO Replace 7.5 Ton HVAC Unit for EMS Building Replace current unit due to age and numerous failures in the last two years. Unit is obsolete and<br />

very hard to acquire parts for and will continue to fail more frequently. Unit needs to be re-located<br />

to below celling level for servicing. 20,000.00<br />

Thacker Avenue Elementary Buildings 3 and 4 door and window replacement Replace current storefront type doors and side windows with hollow metal assemblies, with<br />

supplier providing engineered shop drawings, and assembly will be complete with new mullions,<br />

panic hardware, and closers. The current doors hinges are worn out, and the concealed rod panic<br />

hardware is non functional. 37,000.00<br />

Thacker Avenue Elementary Communication Closet Expansion- MDF Main Distribution Frame (MDF) renovation/retrofit to include: 1) install new voice and data<br />

backboard installed on all walls; 2) reconfiguration of wall fields to identify specific wall field<br />

equipment areas; 3) reconfiguration of grounding system; 4) extend the distance between the<br />

existing two post racks and backboard to meet current standards; 5) install one additional two<br />

post rack to support expansion; 6) install ladder rack for cable support around the perimeter of<br />

the room; 7) install two (2) NEMA L630R clean power receptacles; 8) install above ceiling cabling<br />

support; 8) install new conduit penetrations from exterior to interior; 9) relocation of the UPS<br />

Server Rack; 10) relocate the DX HVAC System; and 11) replace damaged ceiling tiles.<br />

30,000.00<br />

Transportation - Kissimmee Replace Gutter System The gutters have rusted through, have been patched, but are now beyond repair. 25,000.00<br />

Westside K8 Grading/Irrigation/Sod Playfield This campus needs this work, because the <strong>District</strong> has installed relocatable classrooms on much of<br />

their outside PE facilities; the area has no turf and is too rough to allow safe student use. The type<br />

of terrain and soil, (sand) in this area requires irrigation to make it a safe PE area.<br />

125,000.00<br />

Zenith Roof Replacement/HVAC Relocation - Building 1 The area over what was the garden center has had roof leaks for some time. This area was<br />

originally meant to be an enclosed equipment area that would have prevented this, but the<br />

enclosure was cut out as a cost saving effort. This project will enclose this area, and prevent the<br />

water intrusion. 600,000.00<br />

Zenith Oil Separator for Auto Detail - Building 1 Add an oil separator system to treat the water run off from the auto detail operation. The City of<br />

Kissimmee has cited the <strong>District</strong> for this issue. 125,000.00<br />

Contingency 25,000.00<br />

Grand Total 4,300,000.00<br />