NOTES TO DOWNTOWN PUBLIC FACILITIES FUND Phasing:<br />

1 The Shoshone Spring Demonstration Project was the first phase of the Downtown Revitalization Project and<br />

completed in FY2005. This project consisted of 290 feet of the north side of Manitou Manitou Avenue street<br />

frontage from Manitou Jack's to the west corner of the Manitou Lofts and Lofts & Shops at Fountain Creek. A plaza<br />

was constructed around the Shoshone Spring well house which was donated as a conservation easement by the<br />

Manitou Shops and Lofts.<br />

2 Phase 2, was begun in March of 2006 and consists of standard improvements to Manitou Avenue a point 100<br />

feet east of Pawnee Avenue to a point 450 feet west of Pawnee Avenue on both sides of the street. This westerly<br />

point equates to a point 100 feet east of Canon Avenue.<br />

3 Phase 3 was begun in FY2007 and consisted of standard improvements to Manitou Avenue from a point 100 feet<br />

east of Canon Avenue on both sides of Manitou Avenue to the southeast corner of the intersection of Manitou<br />

Avenue and Navajo Avenue on the south side of Manitou Avenue and the beginning point of Phase 1 on the north<br />

side of Manitou Avenue. This phase also included improvement to areas of Canon Avenue and Charles Parker<br />

Place adjacent to the town clock.<br />

4 Phase 4 was begun in FY2008 and consisted of standard improvement on Manitou Avenue from the southwest<br />

corner of Navajo Avenue on the south side of Manitou Avenue and the west end of the Phase 1 project to a point<br />

100 feet east of Ruxton Avenue on both sides of Manitou Avenue.<br />

5A Phase 5A was begun in FY2009 and consisted of standard improvement on Manitou Ave and a traffic circle or<br />

roundabout at the intersection of Manitou Avenue and Ruxton Avenue. The improvement zone began at a point<br />

100 feet east of Ruxton Avenue on both sides of Manitou Avenue and ended at a point 275 feet west of Ruxton<br />

Avenue on both sides of Manitou Avenue.<br />

5B Phase 5B began in FY2012 and consisted of standard improvement on Manitou Avenue from a point 275 feet<br />

west of Ruxton Avenue on both sides of Manitou Avenue to a point 75 feet west of Park Avenue on both sides of<br />

Manitou Avenue. This is funded in part by Federal Transportation Enhancement Grants and Rural Transportation<br />

Capital enhancement allocation.<br />

Notes:<br />

a. Funding of $822,654 provided through the STIP (State Transportation Improvement Plan). The Federal funds are<br />

a grant match of 82.79% to 17.21% as the local agency match. The City is using its capital funds from the PPRTA for<br />

grant match. Numbers have changed from the original budget due to the winning bid being lower than the original<br />

estimate of cost. Federal Funds will cover the construction and administration but not design, so the 82.79% is<br />

derived from the $957,663 plus $8,000 plus $36,000 which is a breakout from the $119,267.<br />

b. The construction cost plus administration adds up to $1,039,327.<br />