Chapter 4 REFERENCES ON GEOMATICS AND LAND SURVEY SERVICES<br />

APPENDIX 4A-5<br />

BQ EXAMPLE - COST ESTIMATE FOR<br />

COASTAL AND WATERWAYS HYDROGRAPHIC SURVEY<br />

Item Description Estd Actual Unit Rate Agreed Actual Remarks/<br />

Qty Qty (RM) Amount Amt Try Item<br />

(a) (b) (c) (d) (e) (f) (g) (h) (I)<br />

1 Mobilization & demobilization of 3 P/day 743.00 2,229.00 14.1<br />

topographic survey equipment<br />

2 Planimetric control <strong>and</strong> connection in 10 km 2,500.00 25,000.00 14.2<br />

built up area<br />

3 Height control <strong>and</strong> connection 10 km 743.00 7,430.00 14.3<br />

4 Topographic strip survey with details 100 ha 99.00 9,900.00 14.8<br />

100m x 10 km coastal strip<br />

5 Bathymetric (Off Shore) Profiling<br />

a) Profiles at 50m 90 km 297.20 26,748.00 14.9.2<br />

b) Profiles at more than 100m 30 km 371.50 11,145.00 14.9.2<br />

c) Extended hydrographic survey 9 km 222.90 2,006.10 14.9.2<br />

up-stream at 25m intervals<br />

6 Direct Reading of Tide Pole 11 No 148.50 1,633.51 14.10.2<br />

a) Installation of Tide Pole 1 no 900.00 900.00<br />

b) Tidal observation 2 P/day 743.00 1,486.00<br />

88,477.61<br />

7 Add 5% Government Service Tax 17,695.52<br />

106,173.13<br />

8 Boat<br />

a) Mobilization 1 no 600.00 600.00<br />

b) Rental 5 P/day 300.00 1,500.00<br />

Estimated Total 108,273.13<br />