LELAND SAYLOR ASSOCIATES<br />

PROJECT: EMERYVILLE CENTER OF COMMUNTIY LIFE LSA JOB NO: 08-121A R5<br />

LOCATION: EMERYVILLE, CA PREPARED BY: MS<br />

CLIENT: FIELD PAOLI CHECKED BY: BS<br />

DESCRIPTION: ALTERNATES DATE: 2/27/2009<br />

CONCEPT ESTIMATE<br />

ALTERNATES QUANTITY UNIT UNIT COST TOTALS<br />

PHOTOVOLTAIC SYSTEM (ALTERNATE 1)<br />

ROOF MOUNTED PHOTOVOLTAIC SYSTEM 21,171 SF 150 3,175,650<br />

SUBTOTAL ALTERNATE 3,175,650<br />

PRORATES 45.06% 1,431,030<br />

TOTAL ALTERNATE 1 4,606,680<br />

KLAUS G61 (ALTERNATE 2)<br />

KLAUS G61 PARKING SYSTEM 90 EA 13,500 1,215,000<br />

BASEMENT PARKING (2,610,669)<br />

SUBTOTAL ALTERNATE (1,395,669)<br />

PRORATES 45.06% (628,925)<br />

TOTAL ALTERNATE 2 (2,024,594)<br />

SPLASHPAD WATER PLAY AREA (ALTERNATE 3)<br />

SPLASH PAD WATER PLAY AREA 1 EA 300,000 300,000<br />

SUBTOTAL ALTERNATE 300,000<br />

PRORATES 45.06% 135,188<br />

TOTAL ALTERNATE 3 435,188