The accelerator shall be housed in a room with adequate shielding and access<br />
control. Prior to its construction, the site layout of the accelerator room should<br />
be approved by AERB. The applicant should also submit the authenticated<br />
documents issued by relevant Government agency showing the status of<br />
ownership/lease of the premises. The Application <strong>for</strong>mat <strong>for</strong> obtaining<br />
regulatory consent <strong>for</strong> Site, Layout and Construction is given in Annexure<br />
29. Detailed safety analysis report should be submitted in the <strong>for</strong>m of<br />
preliminary safety analysis report (PSAR), the <strong>for</strong>mat of which is given in<br />
Appendix 3B-III. AERB issues no separate Consent <strong>for</strong> construction.<br />
However, AERB may inspect the facility while under construction to verify<br />
whether the construction is as per design approved. Installation of accelerator<br />
and preliminary tests on various systems is to be carried out in a phased<br />
manner as per the checkpoints. The quality assurance aspects should be<br />
addressed as per Appendix 3F.<br />
3.7.4.3 Commissioning and Operation<br />
After installation of the industrial accelerator and detailed per<strong>for</strong>mance<br />
verification of the accelerator systems, the Consentee should submit to the<br />
AERB the Application <strong>for</strong> obtaining the Consent <strong>for</strong> commissioning/operation<br />
of industrial accelerator facility as per the <strong>for</strong>mat given in the Annexure 30<br />
along with the FSAR (to be submitted as per Appendix 3D-III). The quality<br />
assurance aspects in the commissioning and operation of the NDT accelerator<br />
should be as per APPENDIX 3F.<br />
AERB may carryout inspection of the industrial accelerator facility if required<br />
prior to commissioning and operation.<br />
Prior to seeing the permission <strong>for</strong> commissioning/operation Consentee should<br />
have:<br />
(i)<br />
(ii)<br />
(iii)<br />
(iv)<br />
Qualified and trained manpower - RSO, certified operator(s)<br />
Personnel monitoring devices<br />
Protection level dosimeters/<strong>Radiation</strong> zone monitor<br />
Emergency response plan and preparedness.<br />
Based on the review of the application, the Acceptance Test Report (to be<br />
submitted as per Appendix 3B) and radiation protection manual (RPM) (to<br />
be in the <strong>for</strong>mat given as per Appendix 3E) and in<strong>for</strong>mation obtained from<br />
inspection, if any, AERB may issue the Consent <strong>for</strong> commissioning/operation<br />
of the industrial accelerator. The Consentee is required to submit periodic<br />
status report to the AERB. Unusual occurrences should be promptly reported<br />
within 24 hours and this should be followed by a detailed investigation report.<br />