14.01.2015 Views

Biomass Feasibility Project Final Report - Xcel Energy

Biomass Feasibility Project Final Report - Xcel Energy

Biomass Feasibility Project Final Report - Xcel Energy

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

e a 75 MW plant using alfalfa stems as fuel, and the EPS/Beck project was to burn cultivated<br />

whole trees. The third project, St. Paul District <strong>Energy</strong>, required the first amendment to the<br />

statute, allowing the use of waste wood as fuel. The utility argued that the high efficiency of a<br />

CHP plant justified a weakening of the fuel standard. The MNVAP and EPS/Beck projects<br />

eventually came to an end when they couldn’t secure financing. NSP cancelled the MNVAP<br />

PPA for non-performance, but the EPS/Beck PPA transferred to other developers with the<br />

Laurentian <strong>Energy</strong> Authority ultimately acquiring it. In the ensuing years, political and market<br />

forces both had a role in deciding which projects would be built under the <strong>Biomass</strong> Mandate.<br />

The <strong>Project</strong>s<br />

The following brief history of <strong>Biomass</strong> Mandate projects is drawn largely from documents from<br />

Public Utilities Commission dockets. Other sources include news reports and interviews with<br />

interested parties. The history of these projects teaches lessons that policy makers and project<br />

developers might heed as they consider the future of biomass power in Minnesota.<br />

MnVAP<br />

Interest in developing a power plant fired by alfalfa stems arose a year or more before the 1994<br />

Prairie Island agreement created the <strong>Biomass</strong> Mandate. In 1993, NSP asked researchers at the<br />

University of Minnesota to identify agricultural products that potentially could be used as fuel.<br />

The researchers quickly settled on alfalfa, and that led NSP to conduct an informational meeting<br />

with farmers in the Southwestern corner of the state that summer. The outlined project would<br />

strip alfalfa leaves from stems and pelletize them for use as high-protein animal feed. The stems<br />

would then be gasified to generate up to 75 MW of power. In the following year, a group of<br />

farmers formed a cooperative called MnVAP, and a study of the project was conducted by<br />

NSP, the University of Minnesota, DOE and EPRI.<br />

Initially MnVAP had seen NSP as a partner, but before the end of 1993 NSP had explained that<br />

the utility would not develop the project themselves but would invite MnVAP to participate in<br />

the competitive bidding process for biomass power projects (Kokmen, 1999). MnVAP chose to<br />

pursue the project, and in mid-1996 won in competitive bidding. They received $4 million from<br />

the Department of <strong>Energy</strong> for design work and permitting ("Northern States", 1996), and became<br />

eligible for up to $40 million in construction financing ("Minnesota Farmers'", 1996). After<br />

negotiating for a year and a half, MnVAP and NSP agreed to a PPA, which they filed in February<br />

of 1998. The Public Utilities Commission then took 14 months to approve the project (PUC,<br />

1999b). The long approval period was due in large part to the intervention of Minnesota <strong>Energy</strong><br />

Consumers (MEC), a coalition of large energy customers, who complained that MnVAP’s power<br />

would cost Minnesota’s ratepayers $30 million more than power from natural gas (PUC, 1998).<br />

Although MEC failed to prevent the PUC’s approval of the PPA, the delay was largely<br />

responsible for the project’s slow unraveling over the course of 1999. In early 1999 Enron, a major<br />

financial backer of the project, pulled out. The Department of <strong>Energy</strong> then followed suit by<br />

freezing its funding of the project (Kokmen, 1999). By the end of the year NSP had terminated its<br />

PPA with MnVAP for nonperformance (NSP, 1999), and MnVAP announced that it would no<br />

longer pursue the project. <strong>Report</strong>s of the episode suggested that the added costs of the<br />

prolonged debate over the PPA caused Enron to pulling out of the project. Others conceded<br />

that this was a factor, but that the project was probably too ambitious, and that PUC’s delay<br />

simply gave the financiers an opportunity to reconsider the risks and costs of the project<br />

(Kokmen, 1999; Mooney, 2000).<br />

MnVAP’s involvement in biomass power continued beyond the termination of their PPA. The coop<br />

actually was close to signing an agreement with Fibrominn for the transfer of their PPA when<br />

Identifying Effective <strong>Biomass</strong> Strategies: Page 91<br />

Quantifying Minnesota’s Resources and Evaluating Future Opportunities

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!