<strong>EPR</strong> <strong>UK</strong><br />

N° NESH-G/2008/en/0123<br />

REV. A PAGE 101 / 257<br />

· Dismantling of the activated and contaminated equipment and structures<br />

· Demolishing and removal of what remains of the facility to a pre-defined end state<br />

which has been agreed with the Regulators and local planning officers, (partial or<br />

total de-licensing). In the reference case strategy the end state is assumed to include<br />

the radiological decontamination of all buildings and their demolition to one meter<br />

below ground level.<br />

The wastes produced by these operations will be removed from the site, possibly after<br />

interim storage on the site. This will almost certainly be the case for ILW. LLW and VLLW<br />

should be removed from site without the need for interim storage.<br />

The corresponding programme is outlined in Figure 26. This is an indicative<br />

decommissioning programme only. Decomissioning programmes will be defined by the<br />

utilities.