<strong>EPR</strong> <strong>UK</strong><br />

N° NESH-G/2008/en/0123<br />

REV. A PAGE 234 / 257<br />

d) Transport container preparation<br />

In the transport container preparation room, before movement of the transport container to<br />

unloading area, the following operations are performed by operations staff standing on a<br />

shielded platform:<br />

· Monitoring of the atmosphere between the inner and outer lids to confirm that the<br />

transport container inner lid remains tight;<br />

· Removal of the outer lid;<br />

· Monitoring of the transport container inner atmosphere (krypton detection), to confirm<br />

that no fuel has been leaking during the transport. In case of krypton detection a<br />

specific procedure will be carried out;<br />

· Unscrewing of the inner lid;<br />

· Fixing of a docking adapter onto the inner lid;<br />

e) Transport container return<br />

The operations described above are performed in approximately reverse order when<br />

preparing fuel assemblies for export from the interim storage facility.<br />

Fuel assemblies unloading and placing into canisters<br />

This part of the facility removes the fuel assemblies from the transport containers and places<br />

them into the fuel storage canisters. The fuel assemblies are sealed in air-tight storage<br />

canisters which are then moved to the storage vault.<br />

a) New canister introduction<br />

An empty canister is introduced into the fuel assemblies transfer tunnel using a handling<br />

crane operated from the handling hall.<br />

b) Transport container inner lid opening<br />

This operation is remotely controlled. After preparation of the transport container, it is<br />

transferred to the docking station and docked to the fuel assemblies unloading cell. The<br />

transport container docking system ensures that the connection between the transport<br />

container internal cavity and the fuel unloading cell is sealed to avoid the spread of<br />

contamination. The transport container inner lid is removed by means of the in-cell jib crane.