Site-Specific Health and Safety Plan (HASP) - Laschools.org
Site-Specific Health and Safety Plan (HASP) - Laschools.org
Site-Specific Health and Safety Plan (HASP) - Laschools.org
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
Type of<br />
Equipment<br />
Minimum<br />
Calibration<br />
Frequency<br />
LAUSD Proposed South Region High School #9 & Middle School #4<br />
Table 11-1<br />
Air Monitoring Equipment<br />
Parameter(s) to be<br />
Measured<br />
11-2<br />
December 2006<br />
<strong>Site</strong> <strong>Specific</strong> <strong>Health</strong> & <strong>Safety</strong> <strong>Plan</strong> (<strong>HASP</strong>)<br />
Minimum<br />
Sampling/Monitoring<br />
Frequency<br />
Sampling/<br />
Monitoring<br />
Locations<br />
PID 1/day Organic vapors Continuous Breathing<br />
Zone <strong>and</strong><br />
Work Area<br />
Colorimetric<br />
Detector Tubes<br />
Combustible<br />
Gas Meter<br />
Personal<br />
Sampling<br />
Pump<br />
Prior to use<br />
flow check<br />
Benzene <strong>and</strong><br />
COC<br />
1/day Oxygen, %LEL,<br />
H2S, <strong>and</strong> CO<br />
2/dayprior<br />
to <strong>and</strong><br />
after use<br />
COCs –<br />
Cal/OSHA<br />
compliance<br />
monitoring;<br />
exposure<br />
monitoring<br />
If PID concentration is<br />
1 ppm or above, every 15<br />
minutes<br />
Breathing<br />
Zone <strong>and</strong><br />
Work Area<br />
Continuous Excavation<br />
Face <strong>and</strong><br />
Work Area<br />
When PID exceeds 5<br />
ppm <strong>and</strong>/or presence of<br />
benzene is detected on<br />
the Draeger ® tube.<br />
Collect at least 3 days of<br />
personal sampling data<br />
for each activity/similar<br />
task In areas where<br />
metals, PCBs, <strong>and</strong> other<br />
COC particulates have<br />
been previously found.<br />
Breathing<br />
Zone<br />
In boreholes, excavation <strong>and</strong> trenches with high <strong>org</strong>anic vapor concentrations (> 100 ppm total<br />
VOCs above background), the excavation will be halted <strong>and</strong> re-evaluated for differing site<br />
conditions (see Table 10-1 for VOC action levels <strong>and</strong> response). This will help allow activities to<br />
be conducted safely in Level D. <strong>Site</strong> personnel will remain upwind of the boreholes <strong>and</strong><br />
excavations at all times, unless air monitoring results determine that downwind activities are<br />
safe.<br />
235