Table J-1<br />
South Region High School #9 <strong>and</strong> Middle School #4 Operable Unite (OU) 1<br />
Alternative 2 (Excavation <strong>and</strong> Off-<strong>Site</strong> Disposal)<br />
Summary of Cost Estimate<br />
CLEANUP - Operable Unit 1 (North of Tweedy Blvd) Quantity (1)<br />
Project <strong>Plan</strong>s <strong>and</strong> Design<br />
Units Cost per Unit Total Cost<br />
Additional Remedial Investigation 0 LS $ 50,000 $ -<br />
Remedial Investigation/<strong>Health</strong> Risk Assessment Reporting 0 LS $ 100,000 $ -<br />
Feasibility Study/Remedial Action <strong>Plan</strong><br />
<strong>Plan</strong>s<br />
0.5 LS $ 100,000 $ 50,000<br />
<strong>Site</strong> Survey 50 hours $ 185 $ 9,250<br />
Excavation & Grading <strong>Plan</strong>s/Specs 1 LS $ 25,000 $ 25,000<br />
Erosion Control <strong>Plan</strong> 1 LS $ 5,000 $ 5,000<br />
RDIP 1 LS $ 50,000 $ 50,000<br />
Environmental QA/QC <strong>Plan</strong> 1 LS $ 8,000 $ 8,000<br />
Public Participation (meetings, fact sheets, etc.) 250 hours $ 150 $ 37,500<br />
Permitting<br />
Subcontractor Submittals<br />
1 LS $ 15,000 $ 15,000<br />
Execution <strong>Plan</strong> Development & Review 1 LS $ 7,000 $ 7,000<br />
<strong>Health</strong> & <strong>Safety</strong> <strong>Plan</strong> 1 LS $ 5,000 $ 5,000<br />
Subcontractor QA/QC <strong>Plan</strong><br />
Subcontractor(s) Mobilization/<strong>Site</strong> Preparation<br />
1 LS $ 5,000 $ 5,000<br />
Mobilization 1 LS $ 25,000 $ 25,000<br />
Perimeter Air Monitoring System Installation / 3 Months Operation 3 Sta $ 3,500 $ 10,500<br />
Temporary Fencing & Delineation (6' Chn Lnk - rented) 500 LF $ 10 $ 5,000<br />
Dust Control 45 Daily $ 850 $ 38,250<br />
Stormwater Pollution <strong>and</strong> Prevention <strong>Plan</strong> 1 LS $ 25,000 $ 25,000<br />
Erosion Control / Stormwater Setup 1,000 Snd Bgs $ 10 $ 10,000<br />
Clearing & Grubbing (with Disposal) 2 acre $ 10,000 $ 20,000<br />
Concrete <strong>and</strong> Asphalt Removal (removal <strong>and</strong> disposal) 5,000 tons $ 50 $ 250,000<br />
Survey / Stake Excavation <strong>Plan</strong><br />
Ab<strong>and</strong>onment & Replacement of Groundwater Wells<br />
100 hours $ 300 $ 30,000<br />
Ab<strong>and</strong>onment of one "C" zone <strong>and</strong> seven "A" zone wells 370 LF $ 73 $ 27,133<br />
Labor 160 hours $ 100 $ 16,000<br />
Driller Subcontractor (7 "A" Zone Wells 1 "C" Zones Well) 370 feet $ 75 $ 27,750<br />
Labor 160 hours $ 100 $ 16,000<br />
Permitting<br />
Shoring & Dewatering<br />
16 per permit $ 200 $ 3,200<br />
Design 1 LS $ 25,000 $ 25,000<br />
Parcel 38 (2) - Soldier Pile shoring for 30 ft excavation 3,600 SF $ 40 $ 144,000<br />
- Leave steel in place 220 Ton $ 900 $ 198,000<br />
- Dewatering 1 LS $ 25,000 $ 25,000<br />
Parcel 39 (3) - Soldier Pile shoring for 30 ft excavation 9,000 SF $ 40 $ 360,000<br />
Parcel 39 (4) - Trench Box shoring for 10 ft excavation 1 LS $ 25,000 $ 25,000<br />
Parcel 29 (5) - Trench Box shoring for 10 ft excavation<br />
Excavation & Disposal<br />
1 LS $ 25,000 $ 25,000<br />
Excavation of Impacted Soils (unsaturated only) 47,610 ton $ 15 $ 714,150<br />
Export Soils/Waste Characterization 79 1/500 CY $ 500 $ 39,675<br />
Excavation of Sloped/Non-Impacted Soils with Stockpile Mgmt (6) Loading, Transportation & Off-<strong>Site</strong> Disposal<br />
13,900 ton $ 17 $ 236,300<br />
RCRA - L<strong>and</strong> ban (0%) - ton $ 198 $ -<br />
RCRA / TSCA - Direct L<strong>and</strong>fill 2,273 ton $ 198 $ 449,955<br />
Non-RCRA (Cal) 4,485 ton $ 100 $ 448,500<br />
RCRA&TSCA - Direct L<strong>and</strong>fill 233 ton $ 240 $ 55,800<br />
Non Hazardous 40,620 ton $ 56 $ 2,274,720<br />
Confirmation Survey 70 hours $ 185 $ 12,950<br />
Field Labor (cleanup field effort, 4 FTEs, 26 weeks) 4,160 hours $ 100 $ 416,000<br />
Air Monitoring Samples (Cr6+, Arsenic, PM10)<br />
Utility Protection<br />
55 3/Sta/Day $ 120 $ 6,600<br />
(7)<br />
Parcel 38 1 LS $ 10,000 $ 10,000<br />
Parcel 39 1 LS $ 10,000 $ 10,000<br />
Adella Avenue 1 LS $ 20,000 $ 20,000<br />
General<br />
Confirmation Sampling (Total SF)<br />
1 LS $ 10,000 $ 10,000<br />
Soil Gas Sampling 1 LS $ 25,000 $ 25,000<br />
Bottom Sampling<br />
200 1/500 sf $ 250 $ 49,927<br />
Sidewall Sampling (1 sample for shallow excavation [>15ft], 2 samples for 116 samples $ 250 $ 29,000<br />
J-1<br />
359