13.2.2 Project Prioritisation<br />
The team participating in prioritisation of the consolidated list of projects<br />
included all relevant departments in the Municipality, and the Department’s<br />
of <strong>Transport</strong>, all of whom were represented on the Working Group for the<br />
preparation of the ITP. Consequently, representatives were familiar with<br />
the different transport components of the ITP having attended various<br />
presentations of the sectoral plans.<br />
The identification and prioritisation of the projects was considered in terms<br />
of the development imperatives of the IDP.<br />
The process also recognised the advent of the 2010 Soccer World Cup and<br />
the need to ensure transport solutions are in place for that event.<br />
In the event of Municipal budget funding shortfalls, some of the prioritised<br />
projects shown in the ITP may need to be delayed for the following year(s).<br />
13.3 Five Year Implementation Programme<br />
The five year programme for transport capital projects is shown in<br />
Table 13.1. Required expenditure for each project is shown on an annual<br />
basis. Current expenditure (2004/05) is also shown.<br />
At the same time it should be recognised that<br />
delaying capital expenditure on needed<br />
projects can place undue pressure on other<br />
related infrastructure with an associated<br />
increase in maintenance costs.<br />
Whilst not specified in the ITP it needs to be<br />
recognised that capital expenditure has the<br />
related need for an increase in the operating<br />
budget; the nature and extent of the operating<br />
budget depending on the type of capital projects<br />
in the programme (eg. new ‘booze buses’ in the<br />
Safety Programme also require manpower and<br />
other resources).<br />
Participants in<br />
project<br />
prioritisation<br />
eThekwini <strong>Integrated</strong> <strong>Transport</strong> <strong>Plan</strong><br />
Summary Report<br />
13.2<br />
Implementation <strong>Plan</strong> 2005-2010<br />
IDP<br />
World Cup 2010