4.4 RAISING RIGID FRAMES<br />

Page 7.1-22<br />

Revision: 2<br />

August 2011<br />

<strong>ERECTION</strong> <strong>AND</strong> <strong>SAFETY</strong> <strong>MANUAL</strong><br />

The intermediate or interior frames nearest the bearing endwall are usually erected fi rst. This bay usually<br />

contains the optional diagonal bracing. The proper completion and plumbing of this fi rst bay, as will be<br />

discussed later, is extremely important to the successful completion of the building.<br />

TEMPORARY<br />

BRACING<br />

BRACED BAY<br />

Although several methods are used to erect rigid frames, it has been found most satisfactory to erect the<br />

columns fi rst, tie them together with the girts and tighten the anchor bolts*. On small spans and short eave<br />

heights, columns can often be set in place by hand without the use of hoisting equipment. Temporary<br />

bracing should always be installed as soon as sections are lifted in place.<br />

* The anchor bolt tension may need to be adjusted to seat the rafter.<br />

ST<strong>AND</strong> COLUMN FIRST<br />

NOTE:<br />

Each worker should be trained to use the safest and most productive erection techniques.<br />

Safety fi rst!<br />

Technical information contained herein is subject to change without notice.