<strong>ERECTION</strong> <strong>AND</strong> <strong>SAFETY</strong> <strong>MANUAL</strong><br />
The correct installation of fl ashing, gutters, and trim cannot be over emphasized. The overall appearance<br />
of the fi nished building depends primarily on the quality of the installation of the fl ashing, gutters and trim.<br />
Keep all gutter and fl ashing lines straight. Make all bends sharp and neat. Be sure edges are not jagged,<br />
dented, crimped, or serrated. End joints and laps must be closely controlled.<br />
RIDGE PANEL<br />
6.0 FLASHING, GUTTER <strong>AND</strong> TRIM<br />
RAKE ANGLE<br />
RAKE TRIM<br />
PEAK BOX<br />
EAVE TRIM<br />
EAVE GUTTER<br />
PEAK BOX<br />
NOTE:<br />
Flashing should be stored off the ground to avoid moisture and handling damage. Elevate one<br />
end of the package above the lower end to encourage drainage in case of rain. Always wear<br />
gloves when handling sheet metal. Safety Firstl<br />