5.13 INSTALLATION OF FIRST ROOF PANEL<br />

Once the eave is prepared, the fi rst roof panel may be installed. Check the erection drawings to determine<br />

the roof overhang at the eave. Set the roof panel in place over the inside closure (after removing the<br />

paper from the mastic) insuring the major ribs of the panel nest properly with the inside closure. Align the<br />

panel edge with the edge of the endwall roof line. With the panel properly placed, secure the panel to the<br />

structure with appropriate fasteners. If the building requires more than one panel per run, do not install<br />

fasteners at the purlin located at the upsiope end of the panel. These fasteners will be installed after the<br />

overlapped panel is installed.<br />

BLANKET<br />

INSULATION<br />

DOUBLE<br />

SIDED TAPE<br />

EAVE STRUT<br />

EAVE FLASHING<br />

WALL PANEL<br />

NOTE:<br />

Do not walk on unsecured panels. substances from roof panels.<br />

Safety fi rst!<br />

C L PANEL RIB<br />

ENDWALL<br />

ROOFLINE<br />

Technical information contained herein is subject to change without notice. Page 7.1-63<br />

Revision: 2<br />

April 2011<br />

*<br />

PANEL<br />

PURLIN<br />

* AS REQUIRED ON<br />

<strong>ERECTION</strong> DRAWINGS