5.13 INSTALLATION OF FIRST ROOF PANEL<br />
Once the eave is prepared, the fi rst roof panel may be installed. Check the erection drawings to determine<br />
the roof overhang at the eave. Set the roof panel in place over the inside closure (after removing the<br />
paper from the mastic) insuring the major ribs of the panel nest properly with the inside closure. Align the<br />
panel edge with the edge of the endwall roof line. With the panel properly placed, secure the panel to the<br />
structure with appropriate fasteners. If the building requires more than one panel per run, do not install<br />
fasteners at the purlin located at the upsiope end of the panel. These fasteners will be installed after the<br />
overlapped panel is installed.<br />
BLANKET<br />
INSULATION<br />
DOUBLE<br />
SIDED TAPE<br />
EAVE STRUT<br />
EAVE FLASHING<br />
WALL PANEL<br />
NOTE:<br />
Do not walk on unsecured panels. substances from roof panels.<br />
Safety fi rst!<br />
C L PANEL RIB<br />
ENDWALL<br />
ROOFLINE<br />
Technical information contained herein is subject to change without notice. Page 7.1-63<br />
Revision: 2<br />
April 2011<br />