To plumb the braced bay without a transit, run a chalk line from out of fl ange to out of fl ange of columns<br />

on the foundation (per drawing). Drop plumb bob(s) from rafter fl ange(s) and square the frame using the<br />

rod bracing for leverage.<br />

To plumb the braced bay lengthwise using a transit, sight in the transit parallel to the base of the frame<br />

columns by using a position a few inches from the frame line (See sketch). Make sure transit is level.<br />

Check frame by reading tape through transit. First bring columns into plumb, then rafters, by adjusting<br />

diagonal bracing. Take all measurements from centerline of fl ange. Take a measurement at the base of<br />

the columns and adjust the bracing to correct the transit reading at the rafter measuring location. Once<br />

the frame is plumb, all connection bolts and anchor bolts should be tightened.<br />

Page 7.1-36<br />

Revision: 2<br />

August 2011<br />

READ WITH TRANSIT<br />

NOTE:<br />

Each worker should be trained to use the safest and most productive erection techniques.<br />

<strong>SAFETY</strong> FIRST!<br />

TRANSIT<br />

Technical information contained herein is subject to change without notice.