6.2 RAKE TRIM & PEAK BOX INSTALLATION<br />
Apply caulking to rake trim as shown below prior to fi nial installation. Rake Trim and/or Peak Box should lap<br />
over rake trim a minimum of 2 inches. Attach to wall panel with #10 fasteners using an outside closure to<br />
seal box at the wall. Attach box to roof with #14 roof fasteners and stitch to trim with blind rivets as shown.<br />
Seal the connection at the roof panel with 1/8” tape sealant (drill 1/4” diameter clearance holes through<br />
plastic for fasteners to prevent cracking).<br />
Splice rake trim with pop rivets at peak box and seal all rake trim laps with sealant to assure a weather-tight<br />
seal.<br />
TAPE SEALANT<br />
CAULK<br />
POP RIVETS<br />
RAKE TRIM PEAK BOX<br />
FIELD NOTCH<br />
TO FIT RIDGE<br />
Technical information contained herein is subject to change without notice. Page 7.1-77<br />
Revision: 2<br />
April 2011