<strong>ERECTION</strong> <strong>AND</strong> <strong>SAFETY</strong> <strong>MANUAL</strong><br />
TYPICAL SECONDARY FRAMING CONNECTION DETAILS<br />
RIGID FRAME COLUMN<br />
GIRT<br />
RIGID FRAME COLUMN<br />
GIRT CLIP<br />
BY-PASS GIRT WITH 3” LAP<br />
FLUSH GIRT<br />
1/2” DIA. A307 BOLTS<br />
1/2” DIA. A307 BOLTS<br />
INTERIOR BAY PURLIN / GIRT FRAMING<br />
NOTE:<br />
The 3” lap requires four (4) 1/2” dia. bolts. The fl ush girt connection requires two (2) or<br />
four (4) 1/2” diameter blots. <strong>SAFETY</strong> FIRST!<br />