05.06.2013 Views

DOE/ORO/2327 Oak Ridge Reservation Annual Site Environmental ...

DOE/ORO/2327 Oak Ridge Reservation Annual Site Environmental ...

DOE/ORO/2327 Oak Ridge Reservation Annual Site Environmental ...

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Tank W1-A Remediation Planned<br />

<strong>Annual</strong> <strong>Site</strong> <strong>Environmental</strong> Report<br />

An area of groundwater contamination resulting from Tank W-1A, called the Core Hole 8 plume, has<br />

been the focus of <strong>DOE</strong> coordinated actions to minimize the release of contaminants since late 1994.<br />

Remediating Tank W-1A has been on hold pending funding, but in FY 2009 it was identified as a<br />

project that would receive ARRA funds.<br />

The Core Hole 8 plume, located in the central portion of the ORNL main plant area, emanates from<br />

contaminated soil surrounding Tank W-1A in the North Tank Farm and migrates westward to a nearby<br />

creek. The principal plume contaminants are strontium-90 and uranium isotopes.<br />

Planning activities in 2009 focused on characterizing the extent and types of contamination as well as<br />

excavation, packaging, and waste transportation considerations. The project is scheduled to be completed<br />

in 2011.<br />

Decommissioning of Non-Reactor Facilities<br />

In FY 2009, <strong>DOE</strong> prepared a remedial design report/remedial action work plan (RDR/RAWP) for<br />

decontamination and decommissioning (D&D) of non-reactor facilities and legacy material removal in the<br />

Bethel Valley Watershed at ORNL. The RDR/RAWP addresses D&D of approximately 180 facilities<br />

including:<br />

• near-term projects funded by ARRA that are planned for completion in 2011, and<br />

• other (non-ARRA-funded) facility D&D and legacy material removal scope planned for<br />

implementation during a 20-plus-year period.<br />

Initiation of Demolition Plans for Building 3026 C&D<br />

In 2009, demolition was initiated on one of the highest hazard excess facilities at ORNL: the 3026<br />

C&D Radioisotope Development Laboratory. This building—one of the original Manhattan Project<br />

facilities—had a footprint of approximately 20,000 ft 2 and contained several hot cells and associated<br />

pipes and ducts that were highly contaminated. The wooden structure in which the hot cells were located<br />

had deteriorated significantly over the years, and a roof failure in 2007 damaged the fire suppression<br />

sprinkler system, requiring deactivation. This presented potential fire hazards to nearby facilities and the<br />

potential for contaminant release if a fire occurred in the facility. <strong>DOE</strong> determined that the resulting risks<br />

warranted implementing a time-critical removal action for the 3026 C&D wooden structure.<br />

In 2009, a high-priority, accelerated project plan was developed by UT-Battelle and approved by<br />

<strong>DOE</strong> to prepare for demolition of the wooden structure. The Waste Handling Plan and associated<br />

sampling and analysis plan/quality assurance project plan was prepared, reviewed, and approved by EPA<br />

and TDEC. The facility’s structural condition was assessed, and shoring was installed to ensure safe<br />

access for workers to most areas of the facility. The facility was surveyed to establish baseline hazardous<br />

material conditions so that appropriate worker protection measures could be identified and implemented.<br />

Samples and analytical data were developed, and a waste profile was prepared and approved for disposal<br />

of the majority of demolition debris at the EMWMF as well as disposal of selected items off-site.<br />

Associated cell piping and ductwork were treated with stabilizing agents to minimize the potential for<br />

release of contaminants during the demolition process. The facility was disconnected from utility systems<br />

(water, steam, air, and ventilation). A subcontract was established with Clauss Construction, LLC, to<br />

demolish the wooden structure. The activities required to prepare for final demolition were initiated and<br />

included removal of asbestos-containing materials (floor tile, transite, thermal insulation); removal of<br />

hazardous materials, such as lead shielding, light bulbs, mercury switches, and oils; and removal of hot<br />

cell piping and ductwork. At the end of FY 2009, final preparations were in progress to begin shipping<br />

and disposing of asbestos-containing debris at the EMWMF. Demolition of the 3026 C&D wooden<br />

structure was completed in early FY 2010. A follow-on project is planned to be initiated later in FY 2010<br />

to demolish the remaining 3026 hot cell structures.<br />

<strong>Oak</strong> <strong>Ridge</strong> National Laboratory 5-85

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!