ATTACHMENT 2<br />
COMMUNITY BUILDINGS — ASSET OVERVIEW<br />
20 Year Resourcing Strategy—Includes S.V. Funding<br />
The chart below shows projected required expenditure over the next 20 years to maintain<br />
Community Building assets in the current condition versus the available funding for this asset,<br />
shown by the black line.<br />
SERVICE LEVELS - BUILT ASSET CONDITION<br />
Business As Usual<br />
3 Year Projected 10 Year Projected<br />
Current<br />
$<br />
M<br />
Financial Strategies Implemented<br />
3 Year Projected 10 Year Projected<br />
NAMS.PLUS2: Community Buildings S2_V2 (updated 11-2-13)<br />
Confidence in Data:<br />
HIGH<br />
MODERATE<br />
LOW<br />
Risks<br />
Increased energy and water costs.<br />
Poor performance of existing facilities.<br />
Funding for Springwood Facilities Development Stages<br />
2 & 3.<br />
Response<br />
Seek additional external grant funding opportunities.<br />
Manage risk by prioritising needs on a yearly basis<br />
Improve condition based maintenance planning<br />
Future DDA planning integrated with other asset<br />
type planning.<br />
<strong>Summary</strong> of Asset Costs<br />
WHOLE OF LIFE GAP<br />
10 YEAR GAP<br />
85