making out the ground and keeping all the references, levels and lining pegs<br />
sealed in cement concrete and execute the work in accordance with those<br />
levels for which he will be responsible throughout the whole period contract.<br />
The few benchmark pillars to be connected with MIDC benchmark will be<br />
constructed by the contractor at the site of works as directed for reference of<br />
various levels in connection with work.<br />
4. CARTING:- The contractor shall provide his own mode of conveyance for<br />
carrying pipes, specials and other sundry materials required for the execution<br />
of the work. The contractor shall provide diversion to the affected existing<br />
road, if required, as directed by the Engineer-in-charge at his own cost.<br />
5. TIME LIMIT:- The time limit for the completion of the work shall be<br />
( 02 ) Two months (including of monsoon) from the date mentioned in the<br />
work order .<br />
6. GENERAL:- The contractor shall be deemed to be thoroughly conversant<br />
with the local condition such as the availability of all construction materials,<br />
skilled and unskilled labour and to have based his rates accordingly for this<br />
work. He shall be deemed to have carefully studied all the specifications and<br />
drawings and followed them before the submission of his <strong>tender</strong>.<br />
7. In case of any discrepancy between the type of working drawings on one<br />
hand and the working of the corresponding item and specification thereof as<br />
per the contract, the later will be deciding for the purpose of actual execution<br />
of items. However, the Executive Engineer (E&M)’s decision should be<br />
obtained in the matter before hand. For a composite item any higher<br />
specification are to be adopted for any component as a result than specified in<br />
the item and specification therefore, extra rate will payable. No major<br />
deviation involving substantial extra outlay will be made without the prior<br />
approval of the Superintending Engineer.<br />
8. A work order book will be maintained by MIDC on site and/or in the<br />
Divisional Office and/or Sub-Division under it. The contractor will sign all<br />
instruction issued by Executive Engineer (E&M) or his representative/his<br />
superior Officers and comply with them. For this purpose the contractor or<br />
Contractor.<br />
Executive Engineer(E&M).