11.10.2014 Views

b-1 tender form - Maharashtra Industrial Development Corporation

b-1 tender form - Maharashtra Industrial Development Corporation

b-1 tender form - Maharashtra Industrial Development Corporation

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

80<br />

the contractor will have to fill the extra excavated depths in layers to bring the correct level by<br />

watering and ramming at his own cost.<br />

1.4 Foundation Preparation : The foundation for column footing and for structural components such as<br />

wall shall not be provided on soft strata covered under this item of excavation. The foundations for<br />

rafts, embedment of pipelines for water supply or drainage or gas may be laid on the foundation<br />

prepared on soft strata. The foundation level even if is confined within the soft layer, the final layer of<br />

excavation watered and brought to the required level and slope by ramming. The contractor shall not<br />

excavate below the line shown in the drawing or as directed. No foundation of any sort shall be laid<br />

unless the Engineerin- charge approves the strata on which foundations are to be laid and passes the<br />

depth of excavation to lay foundation and record the dimensions and elevations and types soils of the<br />

foundation pit, trench excavated, and shall be recorded in the field book adopting system already<br />

explained above.<br />

1.5 Shoring and Strutting : The cost of shoring and strutting shall not be paid separately unless<br />

provided in the contract. The type and designing of shoring shall be decided by the contractor, and<br />

shall get approved from the Engineer in Charge.<br />

Pay Slopes : In lieu of shoring and strutting pay slopes for excavation of trenches/pits shall be<br />

stipulated and paid accordingly.<br />

1.6 Disposal of Excavated Material : All the material obtained from clearing the site or from excavation<br />

shall be the absolute property of MIDC. All materials obtained from clearing the site and excavation<br />

shall be disposed off or spread or stacked within a lead of 50 meters beyond the excavated area as<br />

directed by the Engineer in Charge. Materials suitable for back-filling or other use shall be stacked at<br />

a convenient place within a lead of 50 meters as directed for refilling or reuse. No excavated material<br />

shall be kept within 1.5 m distance from the outer top edge of excavation to avoid the falling of the<br />

stuff in the pit or trench.<br />

Surplus materials shall be used for levelling the ground around as directed within a lead of 50 meters.<br />

If the surplus materials are required to be conveyed and used or stacked beyond 50 meters contractor<br />

shall be paid for extra lead or the extra conveyance as per the terms of contract.<br />

1.7 Dewatering : It is the responsibility of the contractor to remove the water accumulated in the pit or<br />

trench, from sub-soil water or from rains or from any other natural source, by manually or by pumping<br />

out as required. Unless provided for in the contract separately, no payment shall be made for bailing<br />

out the water. The contractor may be required to provide temporary bunds, or provide byepass<br />

arrangements to avoid entering of water in the excavation at his own cost. The drained water shall be<br />

properly disposed off, so as not to cause any damages to the excavated area nor to the surrounding<br />

structures. The contractor shall keep the excavated area dry for measurements and for laying of<br />

foundation mortar or concrete.<br />

1.8 Side Slips and Blows : Even after sufficient care of sides, slips or blows occur, they shall be<br />

removed at contractor’s cost.<br />

1.9 Backfilling : After excavation is completed, measurements recorde by the Engineer-in-charge and<br />

the foundation raft masonry above is constructed or the pipeline is laid, all the shoring shall have to be<br />

removed. The backfilling of the pit or trench to the original level or as shown in the drawing or as<br />

directed shall be made from the selected excavated material stacked separately for that purpose. The<br />

material shall be laid in layers of 15 to 20 cm in thickness, watered and then rammed properly. The<br />

backfilling shall only be done after receiving orders from the Engineer-in-charge and without<br />

damaging the foundation raft or the pipeline etc.<br />

1.10 Protective Measures : All the excavated pits, trenches etc. shall be properly protected from any<br />

accidents by providing strong fencing around. At night red lantern and watchman shall be kept in<br />

proper position to indicate the danger zone. It is the responsibility of the contractor to take the<br />

adequate protective measures and safety of the excavation, people and workmen and surrounding<br />

properties and will have to bear the damages if caused. All the cost of protective measures shall be<br />

included in the item rate.<br />

Contractor.<br />

Executive Engineer(E&M).

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!