11. Supervisory Staff: The contractor shall engage on the work a qualified and<br />
experienced supervisor capable of managing and guiding the work properly.<br />
The Supervisor shall be authorised by the contractor in writing to receive the<br />
orders issued by the Engineer in charge from time to time. The contractor shall<br />
be responsible for carrying out these orders promptly.<br />
12. Work order book : Department will maintain work order book at the site of<br />
work. The contractor or his authorised shall sign all the instructions received<br />
therein, in token of having received the same and shall comply with them<br />
forthwith.<br />
13. Cleaning of site: The contractor shall clear the site of work before starting work<br />
and after completing it. The work of cleaning the site includes cutting of trees,<br />
shrubs, bushes, grass, removing construction such as stacks of various materials,<br />
underground pipes etc. and also rearranging the same as directed by the<br />
Engineer in charge. The cost of cleaning the site as explained above stands<br />
included in the unit rates for various items of work and the department shall not<br />
make any extra payment what so ever on that account. All the materials<br />
obtained in clearing the site shall be the property of the <strong>Corporation</strong>.<br />
14. Progress of Work : The contractor shall carry out the work to the programme<br />
chalked out by the department from time to time. He will also not be allowed to<br />
proceed with the work in scattered manner.<br />
15. Accidents: Should any accidents, fatal or otherwise occurred a detailed report<br />
about the same shall be made promptly by the contractor to Engineer in charge,<br />
Public authorities and relatives of the persons who met with the accident, and all<br />
costs involved therein shall be borne by the contractor.<br />
16. Taxes : The rates quoted by the contractor shall be deemed to include all taxes<br />
octroi and such other charges in force prevailing during the <strong>tender</strong> of work.<br />
17. Housing Arrangement : The contractor shall have to make temporary<br />
arrangements for housing to his employees and the necessary arrangements of<br />
public health are to be provided by the contractor, as provided in the contract<br />
labour ( Regulation and Abolition)Act, 1971.<br />
Contractor.<br />
Executive Engineer(E&M).