62<br />

• Annual adjustments to project cost sharing based on actual growth in each community<br />

as measured by peak day water demand over an average <strong>of</strong> the top 10 peak days each<br />

year; and,<br />

• The new formula would be implemented effective January 1 st, 2010.<br />

Staff believe that the proposed cost sharing formula for growth related (DCC) regional water<br />

capital projects is an improvement in terms <strong>of</strong> equity over our current cost sharing formula.<br />

However, it should be noted that annual adjustments will be made based on average actual<br />

peak day water demand (over 10 maximum days), which places greater emphasis on water<br />

conservation and related control <strong>of</strong> demand to lower one's capital costs, and as <strong>Mission</strong> is<br />

largely unmetered in comparison to Abbotsford which is largely metered, Abbotsford has greater<br />

ability to influence water demand/usage. Strategies should therefore be put in place to lower<br />

peak day demand in <strong>Mission</strong>.<br />

Summar<br />

Based on a staff recommendation, the WSC is now recommending a revised cost sharing<br />

formula for regional growth related water capital projects. The new formula <strong>of</strong>fers greater equity;<br />

however, it does place great emphasis on controlling water demand to lower one's capital costs.<br />

As per the joint utility agreement between <strong>Mission</strong> and Abbotsford, each council is to approve<br />

new cost sharing strategies and changes to the "Ownership & Governance Agreement" and the<br />

"Operation and Maintenance Agreement". Therefore, it is recommended that <strong>District</strong> <strong>of</strong> <strong>Mission</strong><br />

council approve this new Joint Water Capital Cost Sharing Formula, and subsequent<br />

amendments to the Joint Water Supply and Distribution and Sewage Treatment Systems<br />

"Ownership & Governance Agreement" and the "Operation and Maintenance Agreement".<br />

Ken Bjorgaard<br />

GAFINANCEUTILITY TRANSFER \Budget Amendment Reports\Joint Water Capital Cost Sharing Formula 090601.doc<br />

FILE: FIN.BUD.DOM PAGE 2 OF 2<br />