24.04.2015 Views

FINAL SAMPLING AND ANALYSIS PLAN - Documents for Moffett Field

FINAL SAMPLING AND ANALYSIS PLAN - Documents for Moffett Field

FINAL SAMPLING AND ANALYSIS PLAN - Documents for Moffett Field

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

The Engineering Evaluation/Cost Analysis (EE/CA), finalized in July 2008, identified PCBs<br />

as the chemicals of concern and stated that the release of the PCBs needed to be controlled.<br />

In December 2008, the Action Memorandum <strong>for</strong> the Non-Time-Critical Removal Action<br />

(NTCRA) <strong>for</strong> the PCB Contamination at Hangar 1 was completed. The Action<br />

Memorandum selected Alternative 10, the removal of the Hangar 1 siding and application of<br />

a coating to the exposed surfaces, as the preferred removal action. Although PCBs are the<br />

regulatory driver <strong>for</strong> this NTCRA, the presence of lead and asbestos in the exterior and<br />

interior building materials of Hangar 1 will require abatement and disposal compliance, as<br />

well as additional health and safety precautions.<br />

To verify that the removal is executed without the release of PCBs into the environment as a<br />

result of the removal action, soil and sediment samples will be collected to establish baseline<br />

concentrations of PCBs, lead, and asbestos. Baseline/pre-construction samples will be<br />

collected from the soil areas immediately adjacent to Hangar 1 and from any sediment that<br />

may be present in the stormwater trench/conveyance system. The baseline/pre-construction<br />

soil samples will also indicate if soil excavation will be necessary to remove soil where the<br />

PCB concentrations exceed project action limits of 1000 micrograms per kilogram (µg/kg).<br />

Following the removal activities, samples will be collected from the previously sampled soil<br />

areas adjacent to Hangar 1 and from locations on the interior concrete floor of Hangar 1.<br />

Soil samples will be analyzed <strong>for</strong> PCBs, lead, and asbestos. Post-construction confirmation<br />

soil sample concentrations will be compared with the baseline/pre-construction soil sample<br />

concentrations to verify that contaminants were not released into the environment as a result<br />

of the removal action, and to ensure PCBs are below 1000 µg/kg. Concrete wipe samples<br />

will be collected from the interior concrete floor and analyzed <strong>for</strong> PCBs and lead to confirm<br />

that concentrations are below the regulatory limits. Sediment will be removed (washed)<br />

from the stormwater trench/conveyance system as part of the removal action, there<strong>for</strong>e; it is<br />

anticipated that there will not be sediment to sample during the confirmation sampling<br />

event.<br />

Waste streams generated during the removal action will be characterized and sent to the<br />

proper disposal facility. Spent water generated and collected during the removal action will<br />

be treated on site. Pending analytical results and verification that analytical results are below<br />

discharge criteria, the treated spent wash water will be discharged to the Sunnyvale Publicly<br />

Owned Treatment Works (POTW) via the NASA/Ames Sanitary Sewer system.<br />

Final Sampling and Analysis Plan<br />

Installation Restoration Site 29, Hangar 1<br />

Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />

DCN: AMEC-8816-0005-0039<br />

April 2010<br />

Page ii

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!