• Excavation and Disposal of Contaminated Soil: Upon Navy approval, the PCB<br />

contaminated soil will be removed with a loader and place it in roll-off bins <strong>for</strong><br />

transportation to the selected disposal facility. Confirmation samples will be<br />

collected after the excavation until the concentrations <strong>for</strong> total PCB in soil is below<br />

1000 µg/kg. For areas where concentrations of total PCB in baseline/preconstruction<br />

samples exceed 1000 µg/kg, post-construction confirmation samples<br />

<strong>for</strong> asbestos and lead will be collected after PCB contaminated soil has been<br />

removed. The excavation will be backfilled with imported clean fill and compacted.<br />

The clean fill will be analyzed <strong>for</strong> PCBs, SVOCs, TPHs, PAHs, metals, asbestos,<br />

and pH.<br />

• The stormwater trench/conveyance system will be cleaned out and pressure washed<br />

as part of the scope of work, there<strong>for</strong>e; it is unlikely that sediment will be present to<br />

sample <strong>for</strong> comparison purposes with pre-construction samples. Thirty-seven wipe<br />

samples will be collected from the concrete floor of Hangar 1 and analyzed <strong>for</strong><br />

PCBs and lead. If the PCB and lead concentrations are within the regulatory limits<br />

of 10 µg/100 square centimeter (cm 2 ), and 40 micrograms per square foot (µg/ft 2 ),<br />

respectively, then cleanup will be deemed complete in this area. If either PCB or<br />

lead concentrations are not within the regulatory limits then additional pressure<br />

washing will be conducted, followed by additional wipe sampling until complete<br />

cleanup is demonstrated.<br />

• Airfield Beacon and Obstruction Lights, Decontamination, Site Cleanup, and<br />

Demobilization: AMEC will comply with FAA requirements <strong>for</strong> maintenance and<br />

final placement of the beacon and obstruction lights on top of the hangar.<br />

• Waste water generated during the NTCRA will be stored and treated on site prior to<br />

disposal or re-use. Treated water will be sampled every 120,000 gallons analyzed<br />

<strong>for</strong> PCBs, chromium, zinc, lead, asbestos, and pH, as required by the Sunnyvale<br />

POTW discharge permit. Treated water will be re-used <strong>for</strong> construction purposes<br />

when analyses indicate that water does not contain contaminants above federal,<br />

state and local concentration limits.<br />

14.2 Sampling Procedures<br />

14.2.1 Pre-construction/Baseline Soil Sampling Procedure<br />

The following is the soil sampling procedure <strong>for</strong> pre-construction samples:<br />

1. Don a new pair of nitrile gloves.<br />

Final Sampling and Analysis Plan<br />

Installation Restoration Site 29, Hangar 1<br />

Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>,<br />

Cali<strong>for</strong>nia<br />

DCN: AMEC-8816-0005-0039<br />

April 2010<br />

Page 14-3